Energy Projects Near You

Solar, wind and battery projects near Winchelsea (TN36)

3 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TN36 (Rother): 2 approved but not yet running, 1 operational. The largest live scheme is Camber Sands Holiday Park, Lydd Road (0.5 MW rooftop solar, approved on 8 July 2024, not yet built), 7.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

3projects within 10 km
0awaiting a decision
2approved, not running
1operational

Projects within 10 km of TN36

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Little Cheyne Court Wind Farmwind farmwind farm59.8operationalupdated Jul 2009Nov 2002granted Oct 2005Jul 2009Folkestone and Hythe9.9
Smaller schemes under 1 MW, mostly rooftop solar (2)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Camber Sands Holiday Park, Lydd Roadrooftop solarrooftop solar0.5approved, not builtupdated Jul 2024May 2024granted Jul 2024Jul 2024Rother7.6
Ebrofrost, Hobbs Lanerooftop solarrooftop solar—approved, not builtupdated Jan 2026Mar 2025granted May 2025Jan 2026Rother8.4

Distance from the average position of the TN36 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Rooftop solar202000.5
Wind farm100100

MW in pipeline: pending, approved and under-construction capacity.

How Rother decides solar, wind and battery applications

ApplicationsRotherUK
Decided applications (solar, wind, battery)1510,236
Refused4 (27%)19%
Solar refused4 of 1312%
Battery storage refused0 of 216%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

All projects in Rother

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.