Energy Projects Near You

Renewable energy projects in Rother

17 solar, wind or battery projects of 150 kW or more are located in Rother (REPD, July 2026 extract): 4 pending, 10 approved but not running, 1 operational and 2 refused. The council refused 4 of 15 decided applications (27%; UK 19%), with a median 11 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

17projects in the council area
4awaiting a decision
10approved, not running
27%of decisions refused

How Rother decides

ApplicationsRotherUK
Decided applications (solar, wind, battery)1510,236
Refused4 (27%)19%
Solar refused4 of 1312%
Battery storage refused0 of 216%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Projects in Rother

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Eastlands Farm, Catsfield - Catsfield Battery Energy Storage Facilitybattery storagebattery storage240approved, not builtupdated Oct 2025Sep 2024granted Aug 2025Oct 2025
Catsfield Christmas Tree Farm, The Streambattery storagebattery storage99.9application submittedupdated Sep 2025Jul 2025—Sep 2025
St Francis Farmsolar farmsolar farm4operationalupdated May 2015Feb 2014granted Aug 2014May 2015
Catsfield Solar Farmsolar farmsolar farm3.8refused on appealupdated Nov 2016Jul 2015refused Oct 2016Nov 2016
Park Pale House, Mountfield Lane Solar Panel Arraysolar farmsolar farm1.2approved, not builtupdated May 2024Feb 2024granted Apr 2024May 2024
Smaller schemes under 1 MW, mostly rooftop solar (12)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Darvell Bruderhof Community, Brightling Roadsolar farmsolar farm0.5approved, not built may be out of dateupdated Dec 2022Sep 2022granted Nov 2022Dec 2022
Camber Sands Holiday Park, Lydd Roadrooftop solarrooftop solar0.5approved, not builtupdated Jul 2024May 2024granted Jul 2024Jul 2024
Egerton Park Indoor Bowls Club, Bexhillrooftop solarrooftop solar0.3approved, not builtupdated Jan 2026Jun 2025granted Jul 2025Jan 2026
Dale Hill Hotel & Golf Club, Dale Hill - Ground Mounted Solar Panelssolar farmsolar farm0.3application submittedupdated Oct 2025Sep 2025—Oct 2025
Ashburnham Place, Ashburnhamrooftop solarrooftop solar0.2approved, not builtupdated Nov 2024Mar 2024granted Nov 2024Nov 2024
Marley Lanerooftop solarrooftop solar0.2approved, not builtupdated Jan 2024Nov 2023granted Jan 2024Jan 2024
Northpoint, Compass Parkrooftop solarrooftop solar0.2refusedupdated Jan 2026Jun 2025refused Aug 2025Jan 2026
Arlington Energy Battery Storagebattery storagebattery storage—under constructionupdated Jan 2021Oct 2020granted Feb 2021Jan 2021
Robertsbridge Works Solar Panelssolar farmsolar farm—approved, not built may be out of dateupdated Oct 2021Jun 2021granted Sep 2021Oct 2021
Kilnwood Farm - Greener Grid Park & Energy Storagebattery storagebattery storage—application submitted may be out of dateupdated Oct 2021Oct 2021—Oct 2021
Kilnwood Farm, Lunsford Crossbattery storagebattery storage—application submitted may be out of dateupdated Nov 2021Oct 2021—Nov 2021
Ebrofrost, Hobbs Lanerooftop solarrooftop solar—approved, not builtupdated Jan 2026Mar 2025granted May 2025Jan 2026

Postcode districts in Rother

DistrictProjects within 10 kmPendingApprovedOperational
TN195130
TN313021
TN328140
TN33256142
TN363021
TN39226122
TN40216112

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Rother by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.