Energy Projects Near You

Eastlands Farm, Catsfield - Catsfield Battery Energy Storage Facility (240 MW)

Eastlands Farm, Catsfield - Catsfield Battery Energy Storage Facility is a 240 MW battery storage project in Rother, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 4 August 2025, not yet built; the record was last updated on 7 October 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

240 MWbattery storage
approved, not builtstatus in REPD
7 October 2025record last updated
Rothercouncil area

Planning timeline

DateStage
27 September 2024Application submitted
4 August 2025Planning permission granted

Project details

Technology
battery storage (stand-alone storage)
Capacity
240 MW
Status (REPD)
approved, not built
Record last updated
7 October 2025
Operator or applicant
Masdar Arlington Energy
Planning authority
Rother
Planning application reference
RR/2024/1535/P
Address (REPD)
Eastlands Farm, Catsfield, Battle
Council area (by location)
Rother
Time to decision
44 weeks
REPD reference
17826

Who decides

ApplicationsRotherUK
Decided applications (solar, wind, battery)1510,236
Refused4 (27%)19%
Solar refused4 of 1312%
Battery storage refused0 of 216%
Median time from submission to decision11.1 weeks17.0 weeks
Appeals lodged / allowed2 / 0—

Other large projects within 10 km

ProjectTypeMWStatuskm
Catsfield Christmas Tree Farm, The Streambattery storage99.9application submitted<0.1
Moor Hall Farm, Moor Hall Drivebattery storage400approved, not built2.0
Pashley Farm, Ninfield Roadbattery storage130application submitted2.1
Pashley Farmsolar farm11.5operational2.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8915, 0.4416).