Pashley Farm (11.5 MW solar farm)

Pashley Farm is an 11.5 MW solar farm project in Wealden, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 20 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11.5 MWsolar farm
operationalstatus in REPD
20 April 2015record last updated
Wealdencouncil area

Planning timeline

DateStage
4 November 2013Application submitted
10 January 2014Planning permission granted
1 August 2014Construction started
31 March 2015Operational

Project details

Technology
solar farm
Capacity
11.5 MW
Status (REPD)
operational
Record last updated
20 April 2015
Operator or applicant
Bluefield Solar Income Fund
Planning authority
Wealden
Planning application reference
WD/2013/2223/MAJ
Site area
18.0 ha
Address (REPD)
Pashley Farm, Ninfield Road, Bexhill on Sea, East Sussex
Council area (by location)
Wealden
Time to decision
10 weeks
REPD reference
2368

Who decides

ApplicationsWealdenUK
Decided applications (solar, wind, battery)3510,236
Refused4 (11%)19%
Solar refused3 of 2812%
Onshore wind refused1 of 145%
Battery storage refused0 of 616%
Median time from submission to decision11.6 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Pashley Farm, Ninfield Roadbattery storage130application submitted0.2
Moor Hall Farm, Moor Hall Drivebattery storage400approved, not built1.7
Eastlands Farm, Catsfield - Catsfield Battery Energy Storage Facilitybattery storage240approved, not built2.3
Catsfield Christmas Tree Farm, The Streambattery storage99.9application submitted2.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8732, 0.4275).