Renewable energy projects in Wealden

43 solar, wind or battery projects of 150 kW or more are located in Wealden (REPD, July 2026 extract): 7 pending, 25 approved but not running, 9 operational and 1 refused. The council refused 4 of 35 decided applications (11%; UK 19%), with a median 12 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

43projects in the council area
7awaiting a decision
25approved, not running
11%of decisions refused

How Wealden decides

ApplicationsWealdenUK
Decided applications (solar, wind, battery)3510,236
Refused4 (11%)19%
Solar refused3 of 2812%
Onshore wind refused1 of 145%
Battery storage refused0 of 616%
Median time from submission to decision11.6 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Projects in Wealden

Projects of 1 MW and more (19)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Stable Green, Sand Hill Lanebattery storagebattery storage600approved, not builtupdated Nov 2025Jan 2025granted Jul 2025Nov 2025
Moor Hall Farm, Moor Hall Drivebattery storagebattery storage400approved, not builtupdated Nov 2025Jan 2025granted Sep 2025Nov 2025
Pashley Farm, Ninfield Roadbattery storagebattery storage130application submittedupdated Jul 2025Jun 2025—Jul 2025
Lower Claverham Farm & Mount Pleasant Farm, Berwick Solar Farmsolar farmsolar farm49.9refusedupdated Feb 2022Jan 2022refused Mar 2023Feb 2022
Colbrans Farm Estate, Laughtonsolar farmsolar farm40approved, not builtupdated Feb 2026Dec 2024granted Jul 2025Feb 2026
Colbrans Farm Estate, Laughtonbattery storagebattery storage30approved, not builtupdated Feb 2026Dec 2024granted Jul 2025Feb 2026
Pashley Farmsolar farmsolar farm11.5operationalupdated Apr 2015Nov 2013granted Jan 2014Apr 2015
Natewood Farmsolar farmsolar farm8.9operationalupdated Jan 2015Feb 2014granted Apr 2014Jan 2015
Lower Mays Farm Solar Farmbattery storagebattery storage8.8approved, not built may be out of dateupdated Aug 2024Apr 2021granted Jul 2021Aug 2024
Berwick solar farmsolar farmsolar farm8.2operationalupdated Apr 2015Aug 2013granted Oct 2013Apr 2015
Horamsolar farmsolar farm8.1operationalupdated Apr 2015Aug 2014granted Sep 2014Apr 2015
Shepham Lanewind farmwind farm7.5operationalupdated May 2018Feb 2013granted Jan 2015May 2018
Laughton Levelsolar farmsolar farm7operationalupdated Jul 2015Nov 2013granted Mar 2014Jul 2015
Uckfield Solar Electric Forecourtsolar farmsolar farm5.5approved, not built may be out of dateupdated Apr 2021Aug 2020granted Mar 2021Apr 2021
Bentley Estatesolar farmsolar farm5operationalupdated Feb 2017Jun 2014granted Jul 2015Feb 2017
Wilbees Farmsolar farmsolar farm5operationalupdated Nov 2016Sep 2014granted Nov 2014Nov 2016
Lower Mays Farm Solar Farmsolar farmsolar farm5approved, not built may be out of dateupdated Aug 2024Apr 2021granted Jul 2021Aug 2024
Cuckmere Solar Farmsolar farmsolar farm4approved, not built may be out of dateupdated Sep 2020Sep 2015granted Feb 2017Sep 2020
Stone Hillsolar farmsolar farm2.6operationalupdated Jun 2014Oct 2013granted Jan 2014Jun 2014
Smaller schemes under 1 MW, mostly rooftop solar (24)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Knights Farm West - Waste Vehicle Depot & Solar Farmsolar farmsolar farm1application submittedupdated Jan 2026Nov 2025—Jan 2026
Oakwood Business Park, Golden Crossrooftop solarrooftop solar0.8application withdrawnupdated Sep 2024Mar 2024—Sep 2024
Fastener House, Bolton Closerooftop solarrooftop solar0.6approved, not builtupdated Sep 2024Jul 2024granted Sep 2024Sep 2024
Hellingly Hospital, The Driverooftop solarrooftop solar0.3approved, not builtupdated Jan 2026Sep 2025granted Oct 2025Jan 2026
Horder Centre, St Johns Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2024Mar 2024granted May 2024May 2024
Utopia Leisure Centre, Downsview Crescentrooftop solarrooftop solar0.3approved, not builtupdated Nov 2025Jun 2025granted Aug 2025Nov 2025
Swallow Enterprise Park, Diamond Driverooftop solarrooftop solar0.3approved, not builtupdated Dec 2023Oct 2023granted Nov 2023Dec 2023
Ervomex Limited, Sybron Wayrooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Sep 2023granted Oct 2023Oct 2023
Tesco Stores, North Streetrooftop solarrooftop solar0.2application submittedMay 2026——
Chalvington House, Lake View Farmrooftop solarrooftop solar0.2approved, not built may be out of dateupdated Jan 2022Sep 2021granted Dec 2021Jan 2022
Co Op, High Streetrooftop solarrooftop solar0.2approved, not builtupdated Jun 2025Apr 2025granted May 2025Jun 2025
Chilsham Farm Nursery, Chilsham Lanesolar farmsolar farm0.2approved, not builtupdated Apr 2026Dec 2025granted Feb 2026Apr 2026
Silveroaks Farm, Hawkhurst Lanesolar farmsolar farm0.2approved, not builtupdated Apr 2025Jan 2025granted Mar 2025Apr 2025
Pevensey Bay Holiday Park, Pevensey Bayrooftop solarrooftop solar0.2approved, not builtupdated Apr 2026Dec 2025granted Jan 2026Apr 2026
Servomex Limited, Sybron Wayrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025
Lansdowne Secure Childrens Homerooftop solarrooftop solar0.1approved, not built may be out of dateupdated Jun 2021Jun 2021granted Dec 2021Jun 2021
Staverton Nursery, Eastbourne Roadrooftop solarrooftop solar0.1approved, not builtupdated May 2023Mar 2023granted Apr 2023May 2023
Fastener House, Bolton Close - Batter Storagebattery storagebattery storage0application submitted may be out of dateupdated Jul 2024Jul 2024—Jul 2024
Kilnwood Farm, Lunsford Crossbattery storagebattery storage—application submitted may be out of dateupdated Nov 2021Sep 2021—Nov 2021
Olives Farm, Hooebattery storagebattery storage—approved, not builtupdated Jun 2024Dec 2022granted May 2024Jun 2024
Staverton Nursery, Eastbourne Roadbattery storagebattery storage—application submitted may be out of dateupdated Mar 2023Mar 2023—Mar 2023
Boreham Hill, Boreham Streetbattery storagebattery storage—approved, not builtupdated Dec 2024Feb 2024granted Oct 2024Dec 2024
Boship Lions Farm Hotel, Lower Dickersolar farmsolar farm—application submitted may be out of dateupdated May 2024Apr 2024—May 2024
Uckfield Leisure Centrerooftop solarrooftop solar—under constructionupdated Jan 2026——Jan 2026

Postcode districts in Wealden

DistrictProjects within 10 kmPendingApprovedOperational
BN24266146
BN26295157
BN27335188
RH188151
TN52110
TN68080
TN710171
TN206051
TN2114382
TN22223162

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Wealden by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.