Energy Projects Near You

Solar, wind and battery projects near Forest Row (RH18)

8 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of RH18 (Wealden): 1 is waiting for a planning decision, 5 approved but not yet running, 1 operational. The largest live scheme is Horder Centre, St Johns Road (0.3 MW rooftop solar, approved on 9 May 2024, not yet built), 8.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8projects within 10 km
1awaiting a decision
5approved, not running
1operational

Projects within 10 km of RH18

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Worsted Farmsolar farmsolar farm5operationalupdated Apr 2019Sep 2015granted Nov 2016Apr 2019Mid Sussex3.8
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
The Mcindoe Centrerooftop solarrooftop solar0.3refusedupdated Jan 2024Nov 2023refused Jan 2024Jan 2024Mid Sussex5.3
The Mcindoe Centre, Holtye Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2024Feb 2024granted Apr 2024May 2024Mid Sussex5.3
Jubilee Community Centre, Charlwoods Roadrooftop solarrooftop solar0.2approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025Mid Sussex5.7
Eden Vale Farm, Eden Vale Dormans Parksolar farmsolar farm0.2application submitted may be out of dateupdated Jul 2023May 2023—Jul 2023Tandridge6.4
Sewage Disposal Works, Eden Vale - Ground Mounted Solar Panelssolar farmsolar farm0.2approved, not builtupdated Sep 2023May 2023granted Jun 2023Sep 2023Tandridge6.4
Horder Centre, St Johns Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2024Mar 2024granted May 2024May 2024Wealden8.2
Freshfield Lane Brickworks, Freshfield Lanerooftop solarrooftop solar0.3approved, not builtupdated Feb 2026Sep 2025granted Jan 2026Feb 2026Mid Sussex9.4

Distance from the average position of the RH18 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm311100.4
Rooftop solar504011.1

MW in pipeline: pending, approved and under-construction capacity.

How Wealden decides solar, wind and battery applications

ApplicationsWealdenUK
Decided applications (solar, wind, battery)3510,236
Refused4 (11%)19%
Solar refused3 of 2812%
Onshore wind refused1 of 145%
Battery storage refused0 of 616%
Median time from submission to decision11.6 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

All projects in Wealden

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near RH18, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.