Energy Projects Near You

Worsted Farm (5 MW solar farm)

Worsted Farm is a 5 MW solar farm project in Mid Sussex, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 16 April 2019; the record was last updated on 18 April 2019.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
18 April 2019record last updated
Mid Sussexcouncil area

Planning timeline

DateStage
15 September 2015Application submitted
24 December 2015Refused by the planning authority
27 June 2016Appeal lodged
21 November 2016Planning permission granted
21 November 2016Appeal allowed
1 January 2019Construction started
16 April 2019Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
18 April 2019
Operator or applicant
S4N Worsted/
Planning authority
Mid Sussex
Planning application reference
DM/15/3056
Appeal reference
APP/D3830/W/16/3151730
Site area
15.1 ha
Address (REPD)
Land At Worsted Farm, Worsted Lane, East Grinstead, West Sussex
Council area (by location)
Mid Sussex
Time to decision
62 weeks
REPD reference
5633

Who decides

ApplicationsMid SussexUK
Decided applications (solar, wind, battery)1410,236
Refused2 (14%)19%
Solar refused2 of 1112%
Battery storage refused0 of 316%
Median time from submission to decision16.7 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Barrow Green Farmsolar farm5refused6.3
Haxted Mead, Lingfield Solar Farmsolar farm50application submitted7.4
Skinners Farmsolar farm6refused on appeal9.5
Redeham Hall Solar Farmsolar farm5.3refused on appeal9.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1245, 0.0155).