Solar, wind and battery projects near Edenbridge (TN8)
15 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TN8 (Sevenoaks): 2 are waiting for a planning decision, 8 approved but not yet running, 1 operational. The largest live scheme is Haxted Mead, Lingfield Solar Farm (50 MW solar farm, application submitted on 8 July 2025, no decision recorded), 3.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of TN8
Projects of 1 MW and more (6)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Skinners Farmsolar farm | solar farm | 6 | refused on appealupdated Sep 2016 | Oct 2014 | refused Jan 2015 | Sep 2016 | Sevenoaks | 0.6 |
| Gaywood Farmbattery storage | battery storage | 7.5 | permission expiredupdated Jul 2020 | Aug 2017 | granted Mar 2018 | Jul 2020 | Sevenoaks | 2.8 |
| Haxted Mead, Lingfield Solar Farmsolar farm | solar farm | 50 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 | Tandridge | 3.8 |
| Gaywood Solar Farmsolar farm | solar farm | 10.7 | approved, not builtupdated Jan 2024 | Mar 2023 | granted Jan 2024 | Jan 2024 | Tandridge | 4.3 |
| Land at Barrow Green Farmsolar farm | solar farm | 5 | refusedupdated Apr 2015 | Jan 2015 | refused Feb 2015 | Apr 2015 | Tandridge | 5.4 |
| Worsted Farmsolar farm | solar farm | 5 | operationalupdated Apr 2019 | Sep 2015 | granted Nov 2016 | Apr 2019 | Mid Sussex | 9.0 |
Smaller schemes under 1 MW, mostly rooftop solar (9)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Edenbridge Wastewater Treatment Works, Skinners Lanesolar farm | solar farm | 0.6 | approved, not builtupdated Jul 2025 | Jan 2025 | granted Jun 2025 | Jul 2025 | Sevenoaks | 0.8 |
| Commonwork Organic Farms Limited, Bore Placerooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2023 | Sep 2023 | granted Nov 2023 | Nov 2023 | Sevenoaks | 6.1 |
| Commonwork Organic Farms Limited, Bore Placebattery storage | battery storage | — | approved, not builtupdated Nov 2023 | Sep 2023 | granted Nov 2023 | Nov 2023 | Sevenoaks | 6.1 |
| Eden Vale Farm, Eden Vale Dormans Parksolar farm | solar farm | 0.2 | application submitted may be out of dateupdated Jul 2023 | May 2023 | — | Jul 2023 | Tandridge | 8.7 |
| Sewage Disposal Works, Eden Vale - Ground Mounted Solar Panelssolar farm | solar farm | 0.2 | approved, not builtupdated Sep 2023 | May 2023 | granted Jun 2023 | Sep 2023 | Tandridge | 8.8 |
| East Hillrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2023 | Oct 2022 | granted Jun 2023 | Jul 2023 | Tandridge | 8.8 |
| The Mcindoe Centre, Holtye Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2024 | Feb 2024 | granted Apr 2024 | May 2024 | Mid Sussex | 8.8 |
| The Mcindoe Centrerooftop solar | rooftop solar | 0.3 | refusedupdated Jan 2024 | Nov 2023 | refused Jan 2024 | Jan 2024 | Mid Sussex | 8.8 |
| Jubilee Community Centre, Charlwoods Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Nov 2025 | Aug 2025 | granted Oct 2025 | Nov 2025 | Mid Sussex | 9.3 |
Distance from the average position of the TN8 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 8 | 2 | 3 | 1 | 2 | 61.7 |
| Rooftop solar | 5 | 0 | 4 | 0 | 1 | 0.9 |
| Battery storage | 2 | 0 | 1 | 0 | 0 | 0 |
MW in pipeline: pending, approved and under-construction capacity.
How Sevenoaks decides solar, wind and battery applications
| Applications | Sevenoaks | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 11 | 10,236 |
| Refused | 4 (36%) | 19% |
| Solar refused | 2 of 7 | 12% |
| Battery storage refused | 2 of 4 | 16% |
| Median time from submission to decision | 10.3 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 1 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TN8, 1 project has a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.