Energy Projects Near You

Solar, wind and battery projects near East Grinstead (RH19)

11 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of RH19 (Mid Sussex): 3 are waiting for a planning decision, 3 approved but not yet running, 2 operational. The largest live scheme is Haxted Mead, Lingfield Solar Farm (50 MW solar farm, application submitted on 8 July 2025, no decision recorded), 7.7 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

11projects within 10 km
3awaiting a decision
3approved, not running
2operational

Projects within 10 km of RH19

Projects of 1 MW and more (5)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Worsted Farmsolar farmsolar farm5operationalupdated Apr 2019Sep 2015granted Nov 2016Apr 2019Mid Sussex2.1
Land at Barrow Green Farmsolar farmsolar farm5refusedupdated Apr 2015Jan 2015refused Feb 2015Apr 2015Tandridge6.3
Majors Hill/Turners Hill Solar Farmsolar farmsolar farm1.1operationalupdated Jun 2016Jun 2015granted Oct 2015Jun 2016Mid Sussex6.8
Haxted Mead, Lingfield Solar Farmsolar farmsolar farm50application submittedupdated Sep 2025Jul 2025—Sep 2025Tandridge7.7
Redeham Hall Solar Farmsolar farmsolar farm5.3refused on appealupdated Dec 2016Jun 2015refused Jan 2016Dec 2016Tandridge7.8
Smaller schemes under 1 MW, mostly rooftop solar (6)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Jubilee Community Centre, Charlwoods Roadrooftop solarrooftop solar0.2approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025Mid Sussex0.9
The Mcindoe Centrerooftop solarrooftop solar0.3refusedupdated Jan 2024Nov 2023refused Jan 2024Jan 2024Mid Sussex1.2
The Mcindoe Centre, Holtye Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2024Feb 2024granted Apr 2024May 2024Mid Sussex1.2
Sewage Disposal Works, Eden Vale - Ground Mounted Solar Panelssolar farmsolar farm0.2approved, not builtupdated Sep 2023May 2023granted Jun 2023Sep 2023Tandridge1.8
Eden Vale Farm, Eden Vale Dormans Parksolar farmsolar farm0.2application submitted may be out of dateupdated Jul 2023May 2023—Jul 2023Tandridge1.8
Gatwick House, Pound Hillsolar farmsolar farm0.2application submitted may be out of dateupdated Aug 2023Jul 2023—Aug 2023Crawley9.2

Distance from the average position of the RH19 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm8312250.6
Rooftop solar302010.5

MW in pipeline: pending, approved and under-construction capacity.

How Mid Sussex decides solar, wind and battery applications

ApplicationsMid SussexUK
Decided applications (solar, wind, battery)1410,236
Refused2 (14%)19%
Solar refused2 of 1112%
Battery storage refused0 of 316%
Median time from submission to decision16.7 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

All projects in Mid Sussex

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near RH19, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.