Solar, wind and battery projects near Horley (RH6)
28 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of RH6 (Reigate and Banstead): 3 are waiting for a planning decision, 16 approved but not yet running, 2 operational. The largest live scheme is Little Flanchford Farm, Flanchford Road Solar Energy (20 MW solar farm, application submitted on 28 November 2024, no decision recorded), 7.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of RH6
Projects of 1 MW and more (7)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Britannia Crestsolar farm | solar farm | 2.6 | refused on appealupdated May 2016 | Jun 2015 | refused Nov 2015 | May 2016 | Reigate and Banstead | 2.8 |
| Redeham Hall Solar Farmsolar farm | solar farm | 5.3 | refused on appealupdated Dec 2016 | Jun 2015 | refused Jan 2016 | Dec 2016 | Tandridge | 4.0 |
| East Surrey Hospital, Canada Avenue -Solar Panelsrooftop solar | rooftop solar | 2.1 | approved, not builtupdated Dec 2025 | Sep 2025 | granted Nov 2025 | Dec 2025 | Reigate and Banstead | 5.1 |
| Mynthurst Farmsolar farm | solar farm | 13.4 | refused on appealupdated Dec 2015 | Jan 2014 | refused Jun 2014 | Dec 2015 | Mole Valley | 6.4 |
| Land At Flanchford Farmsolar farm | solar farm | 3.1 | refusedupdated Oct 2015 | May 2015 | refused Sep 2015 | Oct 2015 | Reigate and Banstead | 6.9 |
| Little Flanchford Farm, Flanchford Road Solar Energysolar farm | solar farm | 20 | application submittedupdated Jan 2025 | Nov 2024 | — | Jan 2025 | Mole Valley | 7.0 |
| Majors Hill/Turners Hill Solar Farmsolar farm | solar farm | 1.1 | operationalupdated Jun 2016 | Jun 2015 | granted Oct 2015 | Jun 2016 | Mid Sussex | 8.0 |
Smaller schemes under 1 MW, mostly rooftop solar (21)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| South Terminal Car Park Forecourt - Electric Vehicle Charging Forecourtbattery storage | battery storage | — | under constructionupdated Nov 2022 | Jan 2021 | granted Jun 2021 | Nov 2022 | Reigate and Banstead | 0.3 |
| Spire Gatwick Park Hospital, Povey Cross Roadrooftop solar | rooftop solar | 0.1 | refusedupdated Sep 2024 | Jun 2024 | refused Jul 2024 | Sep 2024 | Mole Valley | 1.5 |
| Tesco Extra, Reigate Roadrooftop solar | rooftop solar | 0.4 | approved, not builtupdated May 2026 | Dec 2025 | granted Mar 2026 | May 2026 | Mole Valley | 1.6 |
| Gatwick House, Pound Hillsolar farm | solar farm | 0.2 | application submitted may be out of dateupdated Aug 2023 | Jul 2023 | — | Aug 2023 | Crawley | 2.8 |
| Duxhurst Farm, Duxhurst Lane Solar Farmsolar farm | solar farm | — | approved, not builtupdated Jan 2024 | Jan 2023 | granted Dec 2023 | Jan 2024 | Reigate and Banstead | 3.2 |
| Duxhurst Farm, Duxhurst Lane Solar Farmbattery storage | battery storage | — | approved, not builtupdated Jan 2024 | Jan 2023 | granted Dec 2023 | Jan 2024 | Reigate and Banstead | 3.2 |
| Welland Medical, Hydehurst Lanerooftop solar | rooftop solar | 0.9 | approved, not builtupdated Oct 2022 | Aug 2022 | granted Oct 2022 | Oct 2022 | Crawley | 4.1 |
| Elekta Limited, Fleming Wayrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Dec 2025 | Sep 2025 | granted Nov 2025 | Dec 2025 | Crawley | 4.6 |
| Yodel, County Oak Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2024 | Aug 2024 | granted Aug 2024 | Oct 2024 | Crawley | 4.7 |
| Boeing House, Crawley Business Quarterrooftop solar | rooftop solar | — | approved, not builtupdated Dec 2024 | May 2024 | granted Jun 2024 | Dec 2024 | Crawley | 4.8 |
| Manor Royal, Rowfantrooftop solar | rooftop solar | 0.3 | application withdrawnupdated Oct 2021 | Oct 2021 | — | Oct 2021 | Crawley | 4.8 |
| Vodafone UK, Newton Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2023 | Nov 2022 | granted Jan 2023 | Jan 2023 | Crawley | 4.8 |
| Johnsons Hotel, Woolborough Lane -Solar Panelsrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Dec 2025 | Sep 2025 | granted Nov 2025 | Dec 2025 | Crawley | 5.2 |
| Diva Innovation Centre, Crompton Wayrooftop solar | rooftop solar | — | approved, not builtupdated Aug 2025 | Jun 2025 | granted Aug 2025 | Aug 2025 | Crawley | 5.2 |
| Unit 2, Hollywood Bowl, Crawley Leisure Parkrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2022 | Mar 2022 | granted May 2022 | Mar 2022 | Crawley | 6.2 |
| Woodhatch Place, Cockshot Hill - Micro Energy Storage Systembattery storage | battery storage | 0.2 | approved, not builtupdated Nov 2024 | Aug 2024 | granted Oct 2024 | Nov 2024 | Reigate and Banstead | 6.2 |
| Oriel High Schoolrooftop solar | rooftop solar | 0.2 | operationalupdated Feb 2021 | Jan 2021 | granted Mar 2021 | Feb 2021 | Crawley | 7.6 |
| Surrey Fire And Rescue Headquarters, Wray Park Roadbattery storage | battery storage | 0.2 | application withdrawnupdated Jan 2025 | Oct 2024 | — | Jan 2025 | Reigate and Banstead | 8.1 |
| K2 Crawley Leisure Centre, Pease Pottage Hillrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Dec 2024 | Sep 2024 | granted Nov 2024 | Dec 2024 | Crawley | 8.7 |
| Merstham Community Hub, Merstham Energy Storage Facilitybattery storage | battery storage | 0.2 | application submitted may be out of dateupdated Aug 2024 | Jul 2024 | — | Aug 2024 | Reigate and Banstead | 9.7 |
| The Royal Alexandra And Albert School, Gatton Parkrooftop solar | rooftop solar | 0.3 | approved, not built may be out of dateupdated May 2023 | Mar 2023 | granted May 2023 | May 2023 | Reigate and Banstead | 9.8 |
Distance from the average position of the RH6 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 8 | 2 | 1 | 1 | 4 | 20.2 |
| Rooftop solar | 15 | 0 | 12 | 1 | 1 | 5.7 |
| Battery storage | 5 | 1 | 3 | 0 | 0 | 0.4 |
MW in pipeline: pending, approved and under-construction capacity.
How Reigate and Banstead decides solar, wind and battery applications
| Applications | Reigate and Banstead | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 10 | 10,236 |
| Refused | 2 (20%) | 19% |
| Solar refused | 2 of 7 | 12% |
| Battery storage refused | 0 of 3 | 16% |
| Median time from submission to decision | 13.4 weeks | 17.0 weeks |
| Appeals lodged / allowed | 1 / 0 | — |
All projects in Reigate and Banstead
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near RH6, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.