Redeham Hall Solar Farm (5.3 MW)

Redeham Hall Solar Farm is a 5.3 MW solar farm project in Tandridge, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 5 December 2016; the record was last updated on 23 December 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.3 MWsolar farm
refused on appealstatus in REPD
23 December 2016record last updated
Tandridgecouncil area

Planning timeline

DateStage
10 June 2015Application submitted
15 January 2016Refused by the planning authority
19 March 2016Appeal lodged
5 December 2016Appeal refused

Project details

Technology
solar farm
Capacity
5.3 MW
Status (REPD)
refused on appeal
Record last updated
23 December 2016
Operator or applicant
INRG Solar
Planning authority
Tandridge
Planning application reference
2015/1056
Appeal reference
APP/M3645/W/16/3146389
Site area
9.9 ha
Address (REPD)
Land at Redeham Hall, Smallfield, Horley, Surrey
Council area (by location)
Tandridge
Time to decision
31 weeks
REPD reference
5470

Who decides

Tandridge has 9 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Barrow Green Farmsolar farm5refused8.3
Worsted Farmsolar farm5operational9.8
Haxted Mead, Lingfield Solar Farmsolar farm50application submitted9.9

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1618, -0.1111).