Renewable energy projects in Tandridge
10 solar, wind or battery projects of 150 kW or more are located in Tandridge (REPD, July 2026 extract): 2 pending, 6 approved but not running, 0 operational and 2 refused.
10projects in the council area
2awaiting a decision
6approved, not running
0operational
How Tandridge decides
Tandridge has 9 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.
Projects in Tandridge
Projects of 1 MW and more (5)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated |
|---|---|---|---|---|---|---|
| Haxted Mead, Lingfield Solar Farmsolar farm | solar farm | 50 | application submittedupdated Sep 2025 | Jul 2025 | — | Sep 2025 |
| Caterham Bypassbattery storage | battery storage | 12 | approved, not builtupdated Sep 2024 | Nov 2023 | granted Sep 2024 | Sep 2024 |
| Gaywood Solar Farmsolar farm | solar farm | 10.7 | approved, not builtupdated Jan 2024 | Mar 2023 | granted Jan 2024 | Jan 2024 |
| Redeham Hall Solar Farmsolar farm | solar farm | 5.3 | refused on appealupdated Dec 2016 | Jun 2015 | refused Jan 2016 | Dec 2016 |
| Land at Barrow Green Farmsolar farm | solar farm | 5 | refusedupdated Apr 2015 | Jan 2015 | refused Feb 2015 | Apr 2015 |
Smaller schemes under 1 MW, mostly rooftop solar (5)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated |
|---|---|---|---|---|---|---|
| East Hillrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2023 | Oct 2022 | granted Jun 2023 | Jul 2023 |
| Sewage Disposal Works, Eden Vale - Ground Mounted Solar Panelssolar farm | solar farm | 0.2 | approved, not builtupdated Sep 2023 | May 2023 | granted Jun 2023 | Sep 2023 |
| Eden Vale Farm, Eden Vale Dormans Parksolar farm | solar farm | 0.2 | application submitted may be out of dateupdated Jul 2023 | May 2023 | — | Jul 2023 |
| Godstone Fire Station, Fosterdown - Micro Energy Storage Facilitybattery storage | battery storage | 0.2 | approved, not builtupdated Jan 2025 | Aug 2024 | granted Oct 2024 | Jan 2025 |
| Verge At Succombs Hill, By Wapses Lodge Roundaboutbattery storage | battery storage | 0.2 | approved, not builtupdated Jan 2025 | Sep 2024 | granted Nov 2024 | Jan 2025 |
Postcode districts in Tandridge
| District | Projects within 10 km | Pending | Approved | Operational |
|---|---|---|---|---|
| CR3 | 13 | 2 | 10 | 0 |
| CR6 | 17 | 3 | 14 | 0 |
| RH7 | 17 | 3 | 7 | 2 |
| RH8 | 12 | 1 | 8 | 0 |
| RH9 | 14 | 2 | 8 | 0 |
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Tandridge by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.