Land at Barrow Green Farm (5 MW solar farm)
Land at Barrow Green Farm is a 5 MW solar farm project in Tandridge, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on 25 February 2015; the record was last updated on 7 April 2015.
5 MWsolar farm
refusedstatus in REPD
7 April 2015record last updated
Tandridgecouncil area
Planning timeline
| Date | Stage |
|---|---|
| 13 January 2015 | Application submitted |
| 25 February 2015 | Refused by the planning authority |
Project details
- Technology
- solar farm
- Capacity
- 5 MW
- Status (REPD)
- refused
- Record last updated
- 7 April 2015
- Operator or applicant
- Dowsett Mayhew Planning Partnership
- Planning authority
- Tandridge
- Planning application reference
- 2015/57
- Site area
- 23.3 ha
- Address (REPD)
- Land at Barrow Green Farm, Haxted Road, Lingfield,
- Council area (by location)
- Tandridge
- Time to decision
- 6 weeks
- REPD reference
- 5058
Earlier applications for this site
| Application | MW | Submitted | Outcome |
|---|---|---|---|
| Barrow Green Farm 2014/1014 | 15 | 18 July 2014 | refused 24 October 2014 |
Who decides
Tandridge has 9 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.
Other large projects within 10 km
| Project | Type | MW | Status | km |
|---|---|---|---|---|
| Haxted Mead, Lingfield Solar Farm | solar farm | 50 | application submitted | 1.8 |
| Gaywood Solar Farm | solar farm | 10.7 | approved, not built | 4.7 |
| Gaywood Farm | battery storage | 7.5 | permission expired | 5.2 |
| Skinners Farm | solar farm | 6 | refused on appeal | 5.6 |
| Worsted Farm | solar farm | 5 | operational | 6.3 |
| Redeham Hall Solar Farm | solar farm | 5.3 | refused on appeal | 8.3 |
Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1811, 0.0036).