Energy Projects Near You

Gaywood Farm (7.5 MW battery storage)

Gaywood Farm is a 7.5 MW battery storage project in Sevenoaks, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 27 October 2020; the record was last updated on 27 July 2020.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWbattery storage
permission expiredstatus in REPD
27 July 2020record last updated
Sevenoakscouncil area

Planning timeline

DateStage
18 August 2017Application submitted
12 March 2018Planning permission granted
27 October 2020Permission expired

Project details

Technology
battery storage (stand-alone storage)
Capacity
7.5 MW
Status (REPD)
permission expired
Record last updated
27 July 2020
Operator or applicant
AMDC Energy / Balanced Grid Solutions
Planning authority
Sevenoaks
Planning application reference
17/02668/FUL
Address (REPD)
Land South Of Gaywood Farm, Hole Lane, Edenbridge, Kent
Council area (by location)
Sevenoaks
Time to decision
29 weeks
REPD reference
7113

Who decides

ApplicationsSevenoaksUK
Decided applications (solar, wind, battery)1110,236
Refused4 (36%)19%
Solar refused2 of 712%
Battery storage refused2 of 416%
Median time from submission to decision10.3 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Gaywood Solar Farmsolar farm10.7approved, not built1.7
Skinners Farmsolar farm6refused on appeal2.4
Haxted Mead, Lingfield Solar Farmsolar farm50application submitted3.4
Land at Barrow Green Farmsolar farm5refused5.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.2156, 0.0537).