Solar, wind and battery projects near Godstone (RH9)

14 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of RH9 (Tandridge): 2 are waiting for a planning decision, 8 approved but not yet running. The largest live scheme is Haxted Mead, Lingfield Solar Farm (50 MW solar farm, application submitted on 8 July 2025, no decision recorded), 7.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

14projects within 10 km
2awaiting a decision
8approved, not running
0operational

Projects within 10 km of RH9

Projects of 1 MW and more (7)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Caterham Bypassbattery storagebattery storage12approved, not builtupdated Sep 2024Nov 2023granted Sep 2024Sep 2024Tandridge5.8
Gaywood Solar Farmsolar farmsolar farm10.7approved, not builtupdated Jan 2024Mar 2023granted Jan 2024Jan 2024Tandridge6.7
East Surrey Hospital, Canada Avenue -Solar Panelsrooftop solarrooftop solar2.1approved, not builtupdated Dec 2025Sep 2025granted Nov 2025Dec 2025Reigate and Banstead7.2
Land at Barrow Green Farmsolar farmsolar farm5refusedupdated Apr 2015Jan 2015refused Feb 2015Apr 2015Tandridge7.6
Haxted Mead, Lingfield Solar Farmsolar farmsolar farm50application submittedupdated Sep 2025Jul 2025—Sep 2025Tandridge7.8
Gaywood Farmbattery storagebattery storage7.5permission expiredupdated Jul 2020Aug 2017granted Mar 2018Jul 2020Sevenoaks8.4
Redeham Hall Solar Farmsolar farmsolar farm5.3refused on appealupdated Dec 2016Jun 2015refused Jan 2016Dec 2016Tandridge9.0
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Godstone Fire Station, Fosterdown - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Jan 2025Aug 2024granted Oct 2024Jan 2025Tandridge2.2
East Hillrooftop solarrooftop solar0.2approved, not builtupdated Jul 2023Oct 2022granted Jun 2023Jul 2023Tandridge4.5
Merstham Community Hub, Merstham Energy Storage Facilitybattery storagebattery storage0.2application submitted may be out of dateupdated Aug 2024Jul 2024—Aug 2024Reigate and Banstead6.4
Verge At Succombs Hill, By Wapses Lodge Roundaboutbattery storagebattery storage0.2approved, not builtupdated Jan 2025Sep 2024granted Nov 2024Jan 2025Tandridge7.1
The Royal Alexandra And Albert School, Gatton Parkrooftop solarrooftop solar0.3approved, not built may be out of dateupdated May 2023Mar 2023granted May 2023May 2023Reigate and Banstead8.4
Surrey Fire And Rescue Headquarters, Wray Park Roadbattery storagebattery storage0.2application withdrawnupdated Jan 2025Oct 2024—Jan 2025Reigate and Banstead9.2
Woodhatch Place, Cockshot Hill - Micro Energy Storage Systembattery storagebattery storage0.2approved, not builtupdated Nov 2024Aug 2024granted Oct 2024Nov 2024Reigate and Banstead9.7

Distance from the average position of the RH9 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm4110260.7
Rooftop solar303002.6
Battery storage7140012.8

MW in pipeline: pending, approved and under-construction capacity.

How Tandridge decides solar, wind and battery applications

Tandridge has 9 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

All projects in Tandridge

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near RH9, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.