Mynthurst Farm (13.4 MW solar farm)

Mynthurst Farm is a 13.4 MW solar farm project in Mole Valley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 24 November 2015; the record was last updated on 2 December 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13.4 MWsolar farm
refused on appealstatus in REPD
2 December 2015record last updated
Mole Valleycouncil area

Planning timeline

DateStage
13 January 2014Application submitted
9 June 2014Refused by the planning authority
10 December 2014Appeal lodged
24 November 2015Appeal refused

Project details

Technology
solar farm
Capacity
13.4 MW
Status (REPD)
refused on appeal
Record last updated
2 December 2015
Operator or applicant
Mynthurst Farms
Planning authority
Mole Valley
Planning application reference
MO/2014/0061
Appeal reference
APP/C3620/W/14/3000674
Site area
32.5 ha
Address (REPD)
Land at Mynthurst Farm, Mynthurst, Leigh, Surrey
Council area (by location)
Mole Valley
Time to decision
21 weeks
REPD reference
1773

Who decides

Mole Valley has 9 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Other large projects within 10 km

ProjectTypeMWStatuskm
Little Flanchford Farm, Flanchford Road Solar Energysolar farm20application submitted2.8
Horsham Roadsolar5refused on appeal5.5
Dorking Battery Energy Storage Systembattery storage6operational8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1912, -0.2514).