Horsham Road (5 MW solar)

Horsham Road is a 5 MW solar project in Mole Valley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 10 July 2015; the record was last updated on 4 August 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar
refused on appealstatus in REPD
4 August 2015record last updated
Mole Valleycouncil area

Planning timeline

DateStage
16 July 2014Application submitted
15 October 2014Refused by the planning authority
22 January 2015Appeal lodged
10 July 2015Appeal refused

Project details

Technology
solar
Capacity
5 MW
Status (REPD)
refused on appeal
Record last updated
4 August 2015
Operator or applicant
TGC Renewables
Planning authority
Mole Valley
Planning application reference
MO/2014/1092
Appeal reference
APP/C3620/W/14/3002006
Address (REPD)
Land adjacent to the A24 bypass, to the south west of Beare Green, Mole Valle, Surrey
Council area (by location)
Mole Valley
Time to decision
13 weeks
REPD reference
2025

Who decides

Mole Valley has 9 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Other large projects within 10 km

ProjectTypeMWStatuskm
Mynthurst Farmsolar farm13.4refused on appeal5.5
Dorking Battery Energy Storage Systembattery storage6operational7.1
Little Flanchford Farm, Flanchford Road Solar Energysolar farm20application submitted7.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.1698, -0.3232).