Renewable energy projects in Reigate and Banstead

13 solar, wind or battery projects of 150 kW or more are located in Reigate and Banstead (REPD, July 2026 extract): 1 pending, 9 approved but not running, 0 operational and 2 refused. The council refused 2 of 10 decided applications (20%; UK 19%), with a median 13 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

13projects in the council area
1awaiting a decision
9approved, not running
20%of decisions refused

How Reigate and Banstead decides

ApplicationsReigate and BansteadUK
Decided applications (solar, wind, battery)1010,236
Refused2 (20%)19%
Solar refused2 of 712%
Battery storage refused0 of 316%
Median time from submission to decision13.4 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

Projects in Reigate and Banstead

Projects of 1 MW and more (4)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Rushett Lanebattery storagebattery storage30approved, not builtupdated May 2025Apr 2024granted Apr 2025May 2025
Land At Flanchford Farmsolar farmsolar farm3.1refusedupdated Oct 2015May 2015refused Sep 2015Oct 2015
Britannia Crestsolar farmsolar farm2.6refused on appealupdated May 2016Jun 2015refused Nov 2015May 2016
East Surrey Hospital, Canada Avenue -Solar Panelsrooftop solarrooftop solar2.1approved, not builtupdated Dec 2025Sep 2025granted Nov 2025Dec 2025
Smaller schemes under 1 MW, mostly rooftop solar (9)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
The Royal Alexandra And Albert School, Gatton Parkrooftop solarrooftop solar0.3approved, not built may be out of dateupdated May 2023Mar 2023granted May 2023May 2023
Toyota Limited, Yew Tree Bottom Roadrooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026
Merstham Community Hub, Merstham Energy Storage Facilitybattery storagebattery storage0.2application submitted may be out of dateupdated Aug 2024Jul 2024—Aug 2024
Woodhatch Place, Cockshot Hill - Micro Energy Storage Systembattery storagebattery storage0.2approved, not builtupdated Nov 2024Aug 2024granted Oct 2024Nov 2024
Surrey Fire And Rescue Headquarters, Wray Park Roadbattery storagebattery storage0.2application withdrawnupdated Jan 2025Oct 2024—Jan 2025
South Terminal Car Park Forecourt - Electric Vehicle Charging Forecourtbattery storagebattery storage—under constructionupdated Nov 2022Jan 2021granted Jun 2021Nov 2022
Duxhurst Farm, Duxhurst Lane Solar Farmsolar farmsolar farm—approved, not builtupdated Jan 2024Jan 2023granted Dec 2023Jan 2024
Duxhurst Farm, Duxhurst Lane Solar Farmbattery storagebattery storage—approved, not builtupdated Jan 2024Jan 2023granted Dec 2023Jan 2024
Legal And General Kingswood House, St Monicas Roadrooftop solarrooftop solar—approved, not built may be out of dateupdated Aug 2024Apr 2023granted May 2023Aug 2024

Postcode districts in Reigate and Banstead

DistrictProjects within 10 kmPendingApprovedOperational
KT20182130
RH1213120
RH2192120
RH6283162
SM7263190

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Reigate and Banstead by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.