Energy Projects Near You

Solar, wind and battery projects near Tadworth (KT20)

18 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of KT20 (Reigate and Banstead): 2 are waiting for a planning decision, 13 approved but not yet running. The largest live scheme is Barnett Wood Lane (98 MW battery storage, approved on 24 September 2025, not yet built), 6.8 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

18projects within 10 km
2awaiting a decision
13approved, not running
0operational

Projects within 10 km of KT20

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Rushett Lanebattery storagebattery storage30approved, not builtupdated May 2025Apr 2024granted Apr 2025May 2025Reigate and Banstead2.7
Barnett Wood Lanebattery storagebattery storage98approved, not builtupdated Nov 2025Nov 2024granted Sep 2025Nov 2025Mole Valley6.8
Land At Flanchford Farmsolar farmsolar farm3.1refusedupdated Oct 2015May 2015refused Sep 2015Oct 2015Reigate and Banstead7.4
Little Flanchford Farm, Flanchford Road Solar Energysolar farmsolar farm20application submittedupdated Jan 2025Nov 2024—Jan 2025Mole Valley8.0
Fair Oak Lanebattery storagebattery storage49.9refused on appealupdated Jun 2019Oct 2017—Jun 2019Kingston upon Thames8.7
East Surrey Hospital, Canada Avenue -Solar Panelsrooftop solarrooftop solar2.1approved, not builtupdated Dec 2025Sep 2025granted Nov 2025Dec 2025Reigate and Banstead8.9
Smaller schemes under 1 MW, mostly rooftop solar (12)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Legal And General Kingswood House, St Monicas Roadrooftop solarrooftop solar—approved, not built may be out of dateupdated Aug 2024Apr 2023granted May 2023Aug 2024Reigate and Banstead2.1
Toyota Limited, Yew Tree Bottom Roadrooftop solarrooftop solar0.2approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026Reigate and Banstead3.2
The Royal Alexandra And Albert School, Gatton Parkrooftop solarrooftop solar0.3approved, not built may be out of dateupdated May 2023Mar 2023granted May 2023May 2023Reigate and Banstead4.8
University For The Creative Arts, Ashley Roadrooftop solarrooftop solar—approved, not builtupdated Sep 2023Jul 2023granted Sep 2023Sep 2023Epsom and Ewell5.4
University for the Creative Arts , Ashley Road - GSHP, Battery & Solar Panelsbattery storagebattery storage—approved, not builtupdated Sep 2023Sep 2023granted Jan 2024Sep 2023Epsom and Ewell5.4
Surrey Fire And Rescue Headquarters, Wray Park Roadbattery storagebattery storage0.2application withdrawnupdated Jan 2025Oct 2024—Jan 2025Reigate and Banstead5.4
The Rainbow Centre, East Streetrooftop solarrooftop solar0.2approved, not builtupdated Feb 2025Nov 2024granted Jan 2025Feb 2025Epsom and Ewell6.1
Merstham Community Hub, Merstham Energy Storage Facilitybattery storagebattery storage0.2application submitted may be out of dateupdated Aug 2024Jul 2024—Aug 2024Reigate and Banstead6.6
Richard Doll Building, Cotswold Roadrooftop solarrooftop solar0.5approved, not builtupdated Feb 2024Dec 2023granted Jan 2024Feb 2024Sutton7.1
Woodhatch Place, Cockshot Hill - Micro Energy Storage Systembattery storagebattery storage0.2approved, not builtupdated Nov 2024Aug 2024granted Oct 2024Nov 2024Reigate and Banstead7.2
David Lloyd Leisure Centre, Ewell Roadrooftop solarrooftop solar0.3approved, not builtupdated Nov 2023Sep 2023granted Nov 2023Nov 2023Epsom and Ewell7.7
Bucher Municipal, Curtis Roadrooftop solarrooftop solar0.2approved, not builtupdated May 2023Dec 2022granted Feb 2023May 2023Mole Valley9.7

Distance from the average position of the KT20 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm2100120
Rooftop solar909003.9
Battery storage71401128

MW in pipeline: pending, approved and under-construction capacity.

How Reigate and Banstead decides solar, wind and battery applications

ApplicationsReigate and BansteadUK
Decided applications (solar, wind, battery)1010,236
Refused2 (20%)19%
Solar refused2 of 712%
Battery storage refused0 of 316%
Median time from submission to decision13.4 weeks17.0 weeks
Appeals lodged / allowed1 / 0—

All projects in Reigate and Banstead

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near KT20, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.