Rushett Lane (30 MW battery storage)

Rushett Lane is a 30 MW battery storage project in Reigate and Banstead, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 3 April 2025, not yet built; the record was last updated on 6 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

30 MWbattery storage
approved, not builtstatus in REPD
6 May 2025record last updated
Reigate and Bansteadcouncil area

Planning timeline

DateStage
16 April 2024Application submitted
16 July 2024Refused by the planning authority
25 November 2024Appeal lodged
3 April 2025Planning permission granted
3 April 2025Appeal allowed

Project details

Technology
battery storage (stand-alone storage)
Capacity
30 MW
Status (REPD)
approved, not built
Record last updated
6 May 2025
Operator or applicant
Enso Energy
Planning authority
Epsom and Ewell
Planning application reference
24/00756/FUL
Appeal reference
APP/Z5630/W/24/3354873
Address (REPD)
North Of Rushett Lane Chessington
Council area (by location)
Reigate and Banstead
Time to decision
50 weeks
Name in REPD
Rushett Lane - Battery Storage System
REPD reference
15398

Who decides

Epsom and Ewell has 5 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Other large projects within 10 km

ProjectTypeMWStatuskm
Barnett Wood Lanebattery storage98approved, not built5.6
Fair Oak Lanebattery storage49.9refused on appeal6.5
Cobham Road, Bookham Solar Farmsolar farm49.5approved, not built9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3099, -0.2411).