Cobham Road, Bookham Solar Farm (49.5 MW)

Cobham Road, Bookham Solar Farm is a 49.5 MW solar farm project in Mole Valley, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 May 2026, not yet built; the record was last updated on 15 June 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.5 MWsolar farm
approved, not builtstatus in REPD
15 June 2026record last updated
Mole Valleycouncil area

Planning timeline

DateStage
9 July 2024Application submitted
25 April 2025Refused by the planning authority
21 May 2026Planning permission granted
21 May 2026Appeal allowed

Project details

Technology
solar farm
Capacity
49.5 MW
Status (REPD)
approved, not built
Record last updated
15 June 2026
Operator or applicant
Public Power Solution Limited
Planning authority
Mole Valley
Planning application reference
MO/2024/1048
Site area
49.8 ha
Address (REPD)
Slyfield Farm, Cobham Road, Bookham, Cobham
Council area (by location)
Mole Valley
Time to decision
97 weeks
Name in REPD
Cobham Road, Bookham - Solar Farm
REPD reference
15940

Who decides

Mole Valley has 9 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Other large projects within 10 km

ProjectTypeMWStatuskm
Barnett Wood Lanebattery storage98approved, not built3.8
Fair Oak Lanebattery storage49.9refused on appeal5.3
Dorking Battery Energy Storage Systembattery storage6operational8.8
Rushett Lanebattery storage30approved, not built9.3

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.3088, -0.3751).