Energy Projects Near You

Renewable energy projects in Mid Sussex

15 solar, wind or battery projects of 150 kW or more are located in Mid Sussex (REPD, July 2026 extract): 1 pending, 7 approved but not running, 4 operational and 1 refused. The council refused 2 of 14 decided applications (14%; UK 19%), with a median 17 weeks from submission to decision.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15projects in the council area
1awaiting a decision
7approved, not running
14%of decisions refused

How Mid Sussex decides

ApplicationsMid SussexUK
Decided applications (solar, wind, battery)1410,236
Refused2 (14%)19%
Solar refused2 of 1112%
Battery storage refused0 of 316%
Median time from submission to decision16.7 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Projects in Mid Sussex

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
Bolney Substationbattery storagebattery storage264approved, not builtupdated Oct 2024Mar 2023granted Oct 2024Oct 2024
Libra Energy Stability Projectbattery storagebattery storage100approved, not builtupdated Feb 2025May 2023granted Jan 2025Feb 2025
Coombe Solar Farmsolar farmsolar farm15.3permission expiredupdated Oct 2018Feb 2015granted Aug 2015Oct 2018
Land Parcel North of Goddardssolar farmsolar farm5operationalupdated Mar 2016Apr 2015granted Aug 2015Mar 2016
Land At Chiddinglye Farmsolar farmsolar farm5operationalupdated Feb 2017Jun 2015granted Sep 2015Feb 2017
Worsted Farmsolar farmsolar farm5operationalupdated Apr 2019Sep 2015granted Nov 2016Apr 2019
Goddard's Greensolar farmsolar farm4.4permission expiredupdated May 2020Aug 2018granted Jul 2019May 2020
Majors Hill/Turners Hill Solar Farmsolar farmsolar farm1.1operationalupdated Jun 2016Jun 2015granted Oct 2015Jun 2016
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updated
The Mcindoe Centrerooftop solarrooftop solar0.3refusedupdated Jan 2024Nov 2023refused Jan 2024Jan 2024
The Mcindoe Centre, Holtye Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2024Feb 2024granted Apr 2024May 2024
Freshfield Lane Brickworks, Freshfield Lanerooftop solarrooftop solar0.3approved, not builtupdated Feb 2026Sep 2025granted Jan 2026Feb 2026
Consort Frozen Foods, Consort Wayrooftop solarrooftop solar0.2approved, not builtupdated Sep 2023May 2023granted Sep 2023Sep 2023
The Aspen, Burrell Road - Micro Energy Storage Facilitybattery storagebattery storage0.2approved, not builtupdated Apr 2026Nov 2025granted Feb 2026Apr 2026
Jubilee Community Centre, Charlwoods Roadrooftop solarrooftop solar0.2approved, not builtupdated Nov 2025Aug 2025granted Oct 2025Nov 2025
Princess Royal Hospital, Lewes Roadrooftop solarrooftop solar—application submittedApr 2026——

Postcode districts in Mid Sussex

DistrictProjects within 10 kmPendingApprovedOperational
BN614272
BN45223113
RH1515182
RH1613172
RH1716184
RH1911332

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Projects belong to Mid Sussex by location (nearest postcode to the REPD grid reference); decisions are counted by the planning authority named in REPD.