Coombe Solar Farm (15.3 MW)

Coombe Solar Farm is a 15.3 MW solar farm project in Mid Sussex, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: planning permission expired on 10 August 2018; the record was last updated on 26 October 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15.3 MWsolar farm
permission expiredstatus in REPD
26 October 2018record last updated
Mid Sussexcouncil area

Planning timeline

DateStage
16 February 2015Application submitted
10 August 2015Planning permission granted
10 August 2018Permission expired

Project details

Technology
solar farm
Capacity
15.3 MW
Status (REPD)
permission expired
Record last updated
26 October 2018
Operator or applicant
British Solar Renewables
Planning authority
Mid Sussex
Planning application reference
DM/15/0644
Address (REPD)
Land at Bob Lane and Chapel Road, Twineham
Council area (by location)
Mid Sussex
Time to decision
25 weeks
REPD reference
5095

Who decides

ApplicationsMid SussexUK
Decided applications (solar, wind, battery)1410,236
Refused2 (14%)19%
Solar refused2 of 1112%
Battery storage refused0 of 316%
Median time from submission to decision16.7 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Libra Energy Stability Projectbattery storage100approved, not built0.6
Bolney Substationbattery storage264approved, not built0.6
Bolneybattery storage200approved, not built1.8
Kent Street, Cowfoldbattery storage57refused1.9
Land Parcel North of Goddardssolar farm5operational3.6
Solar Farm & Battery Storage at Cobwood Solar Farmsolar farm49.9approved, not built5.3
Ford Farm (Ashurst)solar farm10operational8.2
Priors Byne Farmsolar farm7.6operational9.3
Horton Landfill Site, Henfield Roadsolar farm12.5application submitted10.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9773, -0.2195).