Ford Farm (Ashurst) (10 MW solar farm)

Ford Farm (Ashurst) is a 10 MW solar farm project in Horsham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 29 February 2016; the record was last updated on 1 April 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

10 MWsolar farm
operationalstatus in REPD
1 April 2016record last updated
Horshamcouncil area

Planning timeline

DateStage
9 December 2013Application submitted
2 May 2014Refused by the planning authority
30 July 2014Appeal lodged
9 September 2015Planning permission granted
9 September 2015Appeal allowed
15 November 2015Construction started
29 February 2016Operational

Project details

Technology
solar farm
Capacity
10 MW
Status (REPD)
operational
Record last updated
1 April 2016
Operator or applicant
Conergy
Planning authority
Horsham
Planning application reference
DC/13/2310
Appeal reference
APP/Z3825/W/14/2222037
Site area
28.3 ha
Address (REPD)
Land North of Sopers Copse Honeybridge Lane Ashurst West Sussex
Council area (by location)
Horsham
Time to decision
91 weeks
REPD reference
1531

Who decides

ApplicationsHorshamUK
Decided applications (solar, wind, battery)2310,236
Refused4 (17%)19%
Solar refused3 of 1912%
Battery storage refused1 of 416%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed3 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Priors Byne Farmsolar farm7.6operational1.4
Huddlestone Farmsolar farm16refused on appeal3.7
Horsham Road Solar Farm & Battery Storagesolar farm49.9application submitted3.7
Land off Hooklands Lanesolar farm5operational4.6
Steyning Battery Energy Storage Facilitybattery storage18abandoned5.3
Horton Landfill Site, Henfield Roadsolar farm12.5application submitted5.6
Kings Barn Farm Energy Barnbattery storage10operational5.9
Solar Farm & Battery Storage at Cobwood Solar Farmsolar farm49.9approved, not built6.2
Bolneybattery storage200approved, not built6.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9428, -0.3223).