Solar, wind and battery projects near Steyning (BN44)
23 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of BN44 (Horsham): 3 are waiting for a planning decision, 12 approved but not yet running, 4 operational. The largest live scheme is Halewick Lane, Sompting Battery-based Energy Storage Facility (50 MW battery storage, under construction since 1 February 2023), 4.9 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Rampion 2 Offshore Wind Farm (Rampion extension) (1,200 MW, approved, not built), 29.6 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of BN44
Projects of 1 MW and more (11)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Kings Barn Farm Energy Barnbattery storage | battery storage | 10 | operationalupdated Mar 2019 | Jul 2016 | — | Mar 2019 | Horsham | 0.4 |
| Steyning Battery Energy Storage Facilitybattery storage | battery storage | 18 | abandonedupdated Mar 2020 | Mar 2018 | — | Mar 2020 | Horsham | 0.7 |
| Horsham Road Solar Farm & Battery Storagesolar farm | solar farm | 49.9 | application submitted may be out of dateupdated Feb 2022 | Jan 2022 | — | Feb 2022 | Horsham | 2.1 |
| Huddlestone Farmsolar farm | solar farm | 16 | refused on appealupdated Feb 2016 | Jan 2014 | refused Apr 2014 | Feb 2016 | Horsham | 2.1 |
| Horton Landfill Site, Henfield Roadsolar farm | solar farm | 12.5 | application submitted may be out of dateupdated Apr 2024 | Apr 2024 | — | Apr 2024 | Horsham | 2.7 |
| Halewick Lane, Sompting Battery-based Energy Storage Facilitybattery storage | battery storage | 50 | under constructionupdated Oct 2022 | Jan 2019 | — | Oct 2022 | Adur | 4.9 |
| Lancing College Campussolar farm | solar farm | 1 | application withdrawnupdated Mar 2019 | Jan 2019 | — | Mar 2019 | Adur | 5.2 |
| Ford Farm (Ashurst)solar farm | solar farm | 10 | operationalupdated Apr 2016 | Dec 2013 | granted Sep 2015 | Apr 2016 | Horsham | 5.8 |
| Priors Byne Farmsolar farm | solar farm | 7.6 | operationalupdated Jan 2017 | Dec 2013 | granted Apr 2015 | Jan 2017 | Horsham | 6.3 |
| Land at Lyons Waysolar farm | solar farm | 3.8 | refusedupdated Apr 2017 | Aug 2015 | refused Nov 2015 | Apr 2017 | Worthing | 6.4 |
| Land off Hooklands Lanesolar farm | solar farm | 5 | operationalupdated Apr 2016 | Aug 2015 | granted Nov 2015 | Apr 2016 | Horsham | 8.1 |
Smaller schemes under 1 MW, mostly rooftop solar (12)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Horsham Road Solar Farm & Battery Storagebattery storage | battery storage | — | application submitted may be out of dateupdated Feb 2022 | Jan 2022 | — | Feb 2022 | Horsham | 2.1 |
| Reception Shoreham Technical Centre Solar PV Panel Panelsrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2024 | Feb 2024 | granted Jun 2024 | Jul 2024 | Adur | 5.9 |
| Glaxo Smithkline, Southdownview Way - Photovoltaic Solar Panelssolar farm | solar farm | — | approved, not builtupdated Aug 2025 | May 2025 | granted Aug 2025 | Aug 2025 | Worthing | 7.2 |
| Worthing College, Sanditon Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Mar 2025 | Jan 2025 | granted Mar 2025 | Mar 2025 | Worthing | 7.4 |
| Unit 24, Star Road Industrial Parkrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Dec 2023 | Dec 2023 | Horsham | 7.5 |
| Unit 1a & B, Star Road Industrial Parkrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Dec 2023 | Dec 2023 | Horsham | 7.5 |
| Start Road Industrial Park, Star Roadrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Feb 2024 | Dec 2023 | granted Feb 2024 | Feb 2024 | Horsham | 7.5 |
| Dunelmrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jul 2025 | Apr 2025 | granted Jul 2025 | Jul 2025 | Adur | 7.6 |
| Chartwell Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jul 2022 | Jul 2022 | granted Sep 2022 | Jul 2022 | Adur | 7.6 |
| Dominion Way Solar photovoltaicsrooftop solar | rooftop solar | 0.4 | approved, not builtupdated Jun 2022 | May 2022 | granted Jul 2022 | Jun 2022 | Worthing | 7.6 |
| St Hughs Monastery, Henfield Roadsolar farm | solar farm | 0.2 | approved, not builtupdated Oct 2022 | Aug 2022 | granted Oct 2022 | Oct 2022 | Horsham | 9.5 |
| Old Shoreham Roadrooftop solar | rooftop solar | 0.6 | approved, not builtupdated May 2025 | Mar 2025 | granted May 2025 | May 2025 | Brighton and Hove | 9.9 |
Distance from the average position of the BN44 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 10 | 2 | 2 | 3 | 2 | 62.6 |
| Rooftop solar | 9 | 0 | 9 | 0 | 0 | 2.6 |
| Battery storage | 4 | 1 | 1 | 1 | 0 | 50 |
MW in pipeline: pending, approved and under-construction capacity.
Offshore wind farms within 40 km
| Wind farm | MW | Status (REPD) | km |
|---|---|---|---|
| Rampion 2 Offshore Wind Farm (Rampion extension) | 1,200 | approved, not builtupdated May 2025 | 29.6 |
| Rampion Offshore Wind Farm (Hastings Zone) | 400 | operationalupdated Dec 2019 | 29.6 |
Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.
How Horsham decides solar, wind and battery applications
| Applications | Horsham | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 23 | 10,236 |
| Refused | 4 (17%) | 19% |
| Solar refused | 3 of 19 | 12% |
| Battery storage refused | 1 of 4 | 16% |
| Median time from submission to decision | 19.0 weeks | 17.0 weeks |
| Appeals lodged / allowed | 3 / 2 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near BN44, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.