Energy Projects Near You

Horsham Road Solar Farm & Battery Storage (49.9 MW)

Horsham Road Solar Farm & Battery Storage is a 49.9 MW solar farm project in Horsham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 21 January 2022, no decision recorded; the record was last updated on 21 February 2022. The application was submitted more than two years ago and is still shown as pending; it may have been decided since. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
application submittedmay be out of datestatus in REPD
21 February 2022record last updated
Horshamcouncil area

The application was submitted more than two years ago and is still shown as pending; it may have been decided since. 32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided.

Planning timeline

DateStage
21 January 2022Application submitted

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
application submitted
Record last updated
21 February 2022
Operator or applicant
Bolney Green Limited
Planning authority
Horsham
Planning application reference
DC/22/0100
Site area
42.2 ha
Address (REPD)
Huddlestone Farm Horsham Road Steyning
Council area (by location)
Horsham
Contracts for Difference
AR6
Name in REPD
Horsham Road - Solar Farm & Battery Storage
REPD reference
10657

The scheme also includes battery storage, recorded separately in REPD (application submitted).

Who decides

ApplicationsHorshamUK
Decided applications (solar, wind, battery)2310,236
Refused4 (17%)19%
Solar refused3 of 1912%
Battery storage refused1 of 416%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed3 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Huddlestone Farmsolar farm16refused on appeal<0.1
Steyning Battery Energy Storage Facilitybattery storage18abandoned1.7
Kings Barn Farm Energy Barnbattery storage10operational2.2
Horton Landfill Site, Henfield Roadsolar farm12.5application submitted2.8
Ford Farm (Ashurst)solar farm10operational3.7
Priors Byne Farmsolar farm7.6operational4.3
Land off Hooklands Lanesolar farm5operational6.5
Halewick Lane, Sompting Battery-based Energy Storage Facilitybattery storage50under construction7.0
Bolneybattery storage200approved, not built8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9095, -0.3217).