Land off Hooklands Lane (5 MW solar farm)

Land off Hooklands Lane is a 5 MW solar farm project in Horsham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 26 March 2016; the record was last updated on 1 April 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
1 April 2016record last updated
Horshamcouncil area

Planning timeline

DateStage
13 August 2015Application submitted
20 November 2015Planning permission granted
10 January 2016Construction started
26 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
1 April 2016
Operator or applicant
Conergy UK
Planning authority
Horsham
Planning application reference
DC/15/1651
Site area
11.0 ha
Address (REPD)
Land off Hooklands Lane, Spear Hill, Ashington, Pulborough
Council area (by location)
Horsham
Time to decision
14 weeks
REPD reference
5578

Who decides

ApplicationsHorshamUK
Decided applications (solar, wind, battery)2310,236
Refused4 (17%)19%
Solar refused3 of 1912%
Battery storage refused1 of 416%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed3 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Priors Byne Farmsolar farm7.6operational3.1
Ford Farm (Ashurst)solar farm10operational4.6
Huddlestone Farmsolar farm16refused on appeal6.5
Horsham Road Solar Farm & Battery Storagesolar farm49.9application submitted6.5
Great Oak Energy Hubbattery storage400approved, not built6.6
Steyning Battery Energy Storage Facilitybattery storage18abandoned8.1
Solar Farm & Battery Storage at Cobwood Solar Farmsolar farm49.9approved, not built8.2
Kings Barn Farm Energy Barnbattery storage10operational8.4
Horton Landfill Site, Henfield Roadsolar farm12.5application submitted9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9524, -0.3855).