Solar Farm & Battery Storage at Cobwood Solar Farm (49.9 MW)

Solar Farm & Battery Storage at Cobwood Solar Farm is a 49.9 MW solar farm project in Horsham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 24 May 2024, not yet built; the record was last updated on 16 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

49.9 MWsolar farm
approved, not builtstatus in REPD
16 February 2026record last updated
Horshamcouncil area

Planning timeline

DateStage
29 November 2023Application submitted
24 May 2024Planning permission granted
24 May 2027Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
49.9 MW
Status (REPD)
approved, not built
Record last updated
16 February 2026
Operator or applicant
Low Carbon UK Solar
Planning authority
Horsham
Planning application reference
DC/23/2172
Site area
73.3 ha
Address (REPD)
Cobwood Solar Farm, Burnthouse Lane, Cowfold, Horsham
Council area (by location)
Horsham
Time to decision
25 weeks
Contracts for Difference
AR7a
Name in REPD
Cobwood Solar Farm, Burnthouse Lane - Solar Farm & Battery Storage
REPD reference
14832

The scheme also includes battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsHorshamUK
Decided applications (solar, wind, battery)2310,236
Refused4 (17%)19%
Solar refused3 of 1912%
Battery storage refused1 of 416%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed3 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Kent Street, Cowfoldbattery storage57refused3.4
Bolneybattery storage200approved, not built4.4
Bolney Substationbattery storage264approved, not built4.7
Great Oak Energy Hubbattery storage400approved, not built5.0
Libra Energy Stability Projectbattery storage100approved, not built5.2
Coombe Solar Farmsolar farm15.3permission expired5.3
Ford Farm (Ashurst)solar farm10operational6.2
Priors Byne Farmsolar farm7.6operational6.5
Land off Hooklands Lanesolar farm5operational8.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9945, -0.2898).