Priors Byne Farm (7.6 MW solar farm)

Priors Byne Farm is a 7.6 MW solar farm project in Horsham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 20 January 2016; the record was last updated on 23 January 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.6 MWsolar farm
operationalstatus in REPD
23 January 2017record last updated
Horshamcouncil area

Planning timeline

DateStage
18 December 2013Application submitted
16 April 2014Refused by the planning authority
15 June 2014Appeal lodged
15 April 2015Planning permission granted
15 April 2015Appeal allowed
1 August 2015Construction started
20 January 2016Operational

Project details

Technology
solar farm
Capacity
7.6 MW
Status (REPD)
operational
Record last updated
23 January 2017
Operator or applicant
Gamma Solar Limited
Planning authority
Horsham
Planning application reference
DC/13/2381
Appeal reference
APP/Z3825/A/14/2219843
Address (REPD)
Priors Byne Farm Bines Road Partridge Green Horsham West Sussex
Council area (by location)
Horsham
Time to decision
69 weeks
REPD reference
1536

Who decides

ApplicationsHorshamUK
Decided applications (solar, wind, battery)2310,236
Refused4 (17%)19%
Solar refused3 of 1912%
Battery storage refused1 of 416%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed3 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Ford Farm (Ashurst)solar farm10operational1.4
Land off Hooklands Lanesolar farm5operational3.1
Huddlestone Farmsolar farm16refused on appeal4.3
Horsham Road Solar Farm & Battery Storagesolar farm49.9application submitted4.3
Steyning Battery Energy Storage Facilitybattery storage18abandoned6.0
Solar Farm & Battery Storage at Cobwood Solar Farmsolar farm49.9approved, not built6.5
Kings Barn Farm Energy Barnbattery storage10operational6.5
Horton Landfill Site, Henfield Roadsolar farm12.5application submitted6.6
Great Oak Energy Hubbattery storage400approved, not built7.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9463, -0.3422).