Great Oak Energy Hub (400 MW battery storage)

Great Oak Energy Hub is a 400 MW battery storage project in Horsham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 28 March 2025, not yet built; the record was last updated on 6 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

400 MWbattery storage
approved, not builtstatus in REPD
6 May 2025record last updated
Horshamcouncil area

Planning timeline

DateStage
17 September 2024Application submitted
28 March 2025Planning permission granted
28 March 2030Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
400 MW
Status (REPD)
approved, not built
Record last updated
6 May 2025
Operator or applicant
Clearstone Energy Limited
Planning authority
Horsham
Planning application reference
DC/24/1289
Address (REPD)
Adj To Shipley Road, Southwater, Horsham
Council area (by location)
Horsham
Time to decision
27 weeks
REPD reference
17245

Who decides

ApplicationsHorshamUK
Decided applications (solar, wind, battery)2310,236
Refused4 (17%)19%
Solar refused3 of 1912%
Battery storage refused1 of 416%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed3 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Solar Farm & Battery Storage at Cobwood Solar Farmsolar farm49.9approved, not built5.0
Land off Hooklands Lanesolar farm5operational6.6
Land at Five Oaks Farmsolar farm5operational6.8
Priors Byne Farmsolar farm7.6operational7.0
Ford Farm (Ashurst)solar farm10operational7.7
Kent Street, Cowfoldbattery storage57refused8.3
Five Oaks Solar Farmsolar farm5operational8.4
Bolneybattery storage200approved, not built9.2
Bolney Substationbattery storage264approved, not built9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.009, -0.3569).