Energy Projects Near You

Solar, wind and battery projects near Billingshurst (RH14)

7 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of RH14 (Horsham): 1 is waiting for a planning decision, 1 approved but not yet running, 4 operational. The largest live scheme is Great Oak Energy Hub (400 MW battery storage, approved on 28 March 2025, not yet built), 9.4 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7projects within 10 km
1awaiting a decision
1approved, not running
4operational

Projects within 10 km of RH14

Projects of 1 MW and more (6)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Wisborough Greensolar farmsolar farm20application submittedupdated May 2025Mar 2025—May 2025Chichester1.7
Land at Five Oaks Farmsolar farmsolar farm5operationalupdated Apr 2016Mar 2015granted Aug 2015Apr 2016Horsham3.9
Five Oaks Solar Farmsolar farmsolar farm5operationalupdated Dec 2012Feb 2011granted Jul 2011Dec 2012Horsham4.0
Maydwell Avenuesolarsolar2.1permission expiredupdated Jul 2016Oct 2012granted May 2013Jul 2016Horsham6.1
Land at Christ’s Hospital Schoolsolar farmsolar farm1.1operationalupdated Dec 2016Apr 2015granted Sep 2015Dec 2016Horsham8.4
Great Oak Energy Hubbattery storagebattery storage400approved, not builtupdated May 2025Sep 2024granted Mar 2025May 2025Horsham9.4
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Brinsbury Campus Stanesolar farmsolar farm0.2operationalupdated Mar 2022Mar 2020granted Jun 2020Mar 2022Horsham4.8

Distance from the average position of the RH14 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm5104020
Solar100000
Battery storage10100400

MW in pipeline: pending, approved and under-construction capacity.

How Horsham decides solar, wind and battery applications

ApplicationsHorshamUK
Decided applications (solar, wind, battery)2310,236
Refused4 (17%)19%
Solar refused3 of 1912%
Battery storage refused1 of 416%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed3 / 2—

All projects in Horsham

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.