Energy Projects Near You

Solar, wind and battery projects near Horsham (RH12)

15 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of RH12 (Horsham): 2 are waiting for a planning decision, 8 approved but not yet running, 4 operational. The largest live scheme is Great Oak Energy Hub (400 MW battery storage, approved on 28 March 2025, not yet built), 7.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

15projects within 10 km
2awaiting a decision
8approved, not running
4operational

Projects within 10 km of RH12

Projects of 1 MW and more (8)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
St Peters Hallrooftop solarrooftop solar1.7operationalupdated Dec 2021Jul 2021granted Oct 2021Dec 2021Horsham2.2
Land at Christ’s Hospital Schoolsolar farmsolar farm1.1operationalupdated Dec 2016Apr 2015granted Sep 2015Dec 2016Horsham5.2
Maydwell Avenuesolarsolar2.1permission expiredupdated Jul 2016Oct 2012granted May 2013Jul 2016Horsham6.1
Smoke Jacks Brickworks, Horsham Road - Ground Mounted Solar Panelssolar farmsolar farm1.6application submittedupdated Jan 2025Dec 2024—Jan 2025Mole Valley7.4
Great Oak Energy Hubbattery storagebattery storage400approved, not builtupdated May 2025Sep 2024granted Mar 2025May 2025Horsham7.9
Land at Five Oaks Farmsolar farmsolar farm5operationalupdated Apr 2016Mar 2015granted Aug 2015Apr 2016Horsham8.0
Five Oaks Solar Farmsolar farmsolar farm5operationalupdated Dec 2012Feb 2011granted Jul 2011Dec 2012Horsham8.3
Solar Farm & Battery Storage at Cobwood Solar Farmsolar farmsolar farm49.9approved, not builtupdated Feb 2026Nov 2023granted May 2024Feb 2026Horsham9.7
Smaller schemes under 1 MW, mostly rooftop solar (7)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Skylark House, St Marks Lanerooftop solarrooftop solar0.1approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Horsham1.3
Sainsburys Supermarket, Worthing Roadrooftop solarrooftop solar0.7approved, not builtupdated Jun 2026Mar 2026granted May 2026Jun 2026Horsham1.7
Fisher Clinical Servicesrooftop solarrooftop solar0.9application submittedMay 2026——Horsham2.5
Broadlands Business Campus, Langhurst Wood Road Solar Panels Phase 3solar farmsolar farm0.5approved, not built may be out of dateupdated May 2023Dec 2022granted May 2023May 2023Horsham3.3
Broadlands Business Campus, Langhurst Wood Road Solar Panels Phase 2solar farmsolar farm—approved, not built may be out of dateupdated May 2023Dec 2022granted May 2023May 2023Horsham3.3
Solar Farm & Battery Storage at Cobwood Solar Farmbattery storagebattery storage—approved, not builtupdated Feb 2026Nov 2023granted May 2024Feb 2026Horsham9.7
K2 Crawley Leisure Centre, Pease Pottage Hillrooftop solarrooftop solar0.4approved, not builtupdated Dec 2024Sep 2024granted Nov 2024Dec 2024Crawley10.0

Distance from the average position of the RH12 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm7133052
Rooftop solar513102.1
Solar100000
Battery storage20200400

MW in pipeline: pending, approved and under-construction capacity.

How Horsham decides solar, wind and battery applications

ApplicationsHorshamUK
Decided applications (solar, wind, battery)2310,236
Refused4 (17%)19%
Solar refused3 of 1912%
Battery storage refused1 of 416%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed3 / 2—

All projects in Horsham

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near RH12, 2 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.