Five Oaks Solar Farm (5 MW)

Five Oaks Solar Farm is a 5 MW solar farm project in Horsham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 1 December 2011; the record was last updated on 6 December 2012.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
6 December 2012record last updated
Horshamcouncil area

Planning timeline

DateStage
15 February 2011Application submitted
22 July 2011Planning permission granted
1 December 2011Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
6 December 2012
Operator or applicant
John Laing Environmental Assets
Planning authority
Horsham
Planning application reference
DC/11/0090
Site area
13.0 ha
Address (REPD)
Haven Road Five Oaks West Sussex
Council area (by location)
Horsham
Time to decision
22 weeks
REPD reference
1581

Who decides

ApplicationsHorshamUK
Decided applications (solar, wind, battery)2310,236
Refused4 (17%)19%
Solar refused3 of 1912%
Battery storage refused1 of 416%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed3 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Land at Five Oaks Farmsolar farm5operational1.7
Wisborough Greensolar farm20application submitted3.2
Great Oak Energy Hubbattery storage400approved, not built8.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0595, -0.446).