Energy Projects Near You

Wisborough Green (20 MW solar farm)

Wisborough Green is a 20 MW solar farm project in Chichester, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: application submitted on 27 March 2025, no decision recorded; the record was last updated on 2 May 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

20 MWsolar farm
application submittedstatus in REPD
2 May 2025record last updated
Chichestercouncil area

Planning timeline

DateStage
27 March 2025Application submitted

Project details

Technology
solar farm
Capacity
20 MW
Status (REPD)
application submitted
Record last updated
2 May 2025
Operator or applicant
Renewable Connections Developments Limited
Planning authority
Chichester
Planning application reference
25/00658/FUL
Site area
41.4 ha
Address (REPD)
The East Of The B2133 Wisborough Green Billingshurst
Council area (by location)
Chichester
Name in REPD
Wisborough Green - Solar Photovoltaic Panels
REPD reference
16113

Who decides

ApplicationsChichesterUK
Decided applications (solar, wind, battery)2510,236
Refused4 (16%)19%
Solar refused4 of 2412%
Battery storage refused0 of 116%
Median time from submission to decision12.9 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Five Oaks Solar Farmsolar farm5operational3.2
Land at Five Oaks Farmsolar farm5operational3.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (51.0483, -0.4887).