Energy Projects Near You

Solar, wind and battery projects near Pulborough (RH20)

3 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of RH20 (Horsham): 3 operational. The largest scheme is Priors Byne Farm (7.6 MW solar farm, operational since 20 January 2016), 9.0 km away. Offshore, 2 wind farms are recorded within 40 km; the nearest is Rampion 2 Offshore Wind Farm (Rampion extension) (1,200 MW, approved, not built), 38.9 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

3projects within 10 km
0awaiting a decision
0approved, not running
3operational

Projects within 10 km of RH20

Projects of 1 MW and more (2)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Land off Hooklands Lanesolar farmsolar farm5operationalupdated Apr 2016Aug 2015granted Nov 2015Apr 2016Horsham6.2
Priors Byne Farmsolar farmsolar farm7.6operationalupdated Jan 2017Dec 2013granted Apr 2015Jan 2017Horsham9.0
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Brinsbury Campus Stanesolar farmsolar farm0.2operationalupdated Mar 2022Mar 2020granted Jun 2020Mar 2022Horsham5.9

Distance from the average position of the RH20 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm300300

MW in pipeline: pending, approved and under-construction capacity.

Offshore wind farms within 40 km

Wind farmMWStatus (REPD)km
Rampion 2 Offshore Wind Farm (Rampion extension)1,200approved, not builtupdated May 202538.9
Rampion Offshore Wind Farm (Hastings Zone)400operationalupdated Dec 201938.9

Operational, approved and pending offshore wind farms; distance from the district centre to the REPD grid reference of each wind farm (one point per site, so the nearest turbines can be closer or further). All offshore wind farms in UK waters.

How Horsham decides solar, wind and battery applications

ApplicationsHorshamUK
Decided applications (solar, wind, battery)2310,236
Refused4 (17%)19%
Solar refused3 of 1912%
Battery storage refused1 of 416%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed3 / 2—

All projects in Horsham

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.