Huddlestone Farm (16 MW solar farm)

Huddlestone Farm is a 16 MW solar farm project in Horsham, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 26 January 2016; the record was last updated on 5 February 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

16 MWsolar farm
refused on appealstatus in REPD
5 February 2016record last updated
Horshamcouncil area

Planning timeline

DateStage
7 January 2014Application submitted
16 April 2014Refused by the planning authority
15 May 2014Appeal lodged
26 January 2016Appeal refused

Project details

Technology
solar farm
Capacity
16 MW
Status (REPD)
refused on appeal
Record last updated
5 February 2016
Operator or applicant
Huddlestone Farm Solar Park
Planning authority
Horsham
Planning application reference
DC/13/2420
Appeal reference
APP/Z3825/W/14/2218035
Site area
35.2 ha
Address (REPD)
Huddlestone Farm, Horsham Road, Steyning
Council area (by location)
Horsham
Time to decision
14 weeks
REPD reference
1488

Who decides

ApplicationsHorshamUK
Decided applications (solar, wind, battery)2310,236
Refused4 (17%)19%
Solar refused3 of 1912%
Battery storage refused1 of 416%
Median time from submission to decision19.0 weeks17.0 weeks
Appeals lodged / allowed3 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Horsham Road Solar Farm & Battery Storagesolar farm49.9application submitted<0.1
Steyning Battery Energy Storage Facilitybattery storage18abandoned1.7
Kings Barn Farm Energy Barnbattery storage10operational2.2
Horton Landfill Site, Henfield Roadsolar farm12.5application submitted2.8
Ford Farm (Ashurst)solar farm10operational3.7
Priors Byne Farmsolar farm7.6operational4.3
Land off Hooklands Lanesolar farm5operational6.5
Halewick Lane, Sompting Battery-based Energy Storage Facilitybattery storage50under construction7.0
Bolneybattery storage200approved, not built8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9097, -0.3219).