Energy Projects Near You

Libra Energy Stability Project (100 MW battery storage)

Libra Energy Stability Project is a 100 MW battery storage project in Mid Sussex, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 31 January 2025, not yet built; the record was last updated on 10 February 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

100 MWbattery storage
approved, not builtstatus in REPD
10 February 2025record last updated
Mid Sussexcouncil area

Planning timeline

DateStage
3 May 2023Application submitted
31 January 2025Planning permission granted
31 January 2032Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
100 MW
Status (REPD)
approved, not built
Record last updated
10 February 2025
Operator or applicant
Lightrock Power
Planning authority
Mid Sussex
Planning application reference
DM/23/1184
Address (REPD)
Coombe Farm, Bob Lane, Twineham, Haywards Heath
Council area (by location)
Mid Sussex
Time to decision
91 weeks
Name in REPD
Libra Energy Stability Project - Battery Energy Storage
REPD reference
12443

Who decides

ApplicationsMid SussexUK
Decided applications (solar, wind, battery)1410,236
Refused2 (14%)19%
Solar refused2 of 1112%
Battery storage refused0 of 316%
Median time from submission to decision16.7 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bolney Substationbattery storage264approved, not built0.5
Coombe Solar Farmsolar farm15.3permission expired0.6
Bolneybattery storage200approved, not built1.3
Kent Street, Cowfoldbattery storage57refused1.8
Land Parcel North of Goddardssolar farm5operational3.9
Solar Farm & Battery Storage at Cobwood Solar Farmsolar farm49.9approved, not built5.2
Ford Farm (Ashurst)solar farm10operational7.6
Priors Byne Farmsolar farm7.6operational8.8
Horton Landfill Site, Henfield Roadsolar farm12.5application submitted9.4

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9732, -0.2244).