Energy Projects Near You

Land Parcel North of Goddards (5 MW solar farm)

Land Parcel North of Goddards is a 5 MW solar farm project in Mid Sussex, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 30 March 2016; the record was last updated on 22 March 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
22 March 2016record last updated
Mid Sussexcouncil area

Planning timeline

DateStage
7 April 2015Application submitted
7 August 2015Planning permission granted
5 February 2016Construction started
30 March 2016Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
22 March 2016
Operator or applicant
INRG Solar
Planning authority
Mid Sussex
Planning application reference
DM/15/1518
Site area
11.7 ha
Address (REPD)
Land Parcel North Of Goddards, Cuckfield Road, Ansty, Haywards Heath, West Sussex
Council area (by location)
Mid Sussex
Time to decision
17 weeks
REPD reference
5140

Who decides

ApplicationsMid SussexUK
Decided applications (solar, wind, battery)1410,236
Refused2 (14%)19%
Solar refused2 of 1112%
Battery storage refused0 of 316%
Median time from submission to decision16.7 weeks17.0 weeks
Appeals lodged / allowed1 / 1—

Other large projects within 10 km

ProjectTypeMWStatuskm
Coombe Solar Farmsolar farm15.3permission expired3.6
Libra Energy Stability Projectbattery storage100approved, not built3.9
Bolney Substationbattery storage264approved, not built4.2
Bolneybattery storage200approved, not built5.2
Kent Street, Cowfoldbattery storage57refused5.4
Land At Chiddinglye Farmsolar farm5operational7.5
Solar Farm & Battery Storage at Cobwood Solar Farmsolar farm49.9approved, not built8.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.977, -0.1684).