Solar, wind and battery projects near Uckfield (TN22)
22 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TN22 (Wealden): 3 are waiting for a planning decision, 16 approved but not yet running, 2 operational. The largest live scheme is Stable Green, Sand Hill Lane (600 MW battery storage, approved on 31 July 2025, not yet built), 5.0 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of TN22
Projects of 1 MW and more (8)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Uckfield Solar Electric Forecourtsolar farm | solar farm | 5.5 | approved, not built may be out of dateupdated Apr 2021 | Aug 2020 | granted Mar 2021 | Apr 2021 | Wealden | 2.1 |
| Stable Green, Sand Hill Lanebattery storage | battery storage | 600 | approved, not builtupdated Nov 2025 | Jan 2025 | granted Jul 2025 | Nov 2025 | Wealden | 5.0 |
| Bentley Estatesolar farm | solar farm | 5 | operationalupdated Feb 2017 | Jun 2014 | granted Jul 2015 | Feb 2017 | Wealden | 5.4 |
| Tomkins Farmsolar farm | solar farm | 5 | refused on appealupdated May 2016 | Apr 2015 | refused Jul 2015 | May 2016 | Lewes | 7.8 |
| Land at Upper Clayhill Farmsolar farm | solar farm | 4.9 | operationalupdated Dec 2015 | Oct 2014 | granted Dec 2014 | Dec 2015 | Lewes | 8.0 |
| Ringmer Solar array/Battery storagesolar farm | solar farm | 17 | approved, not built may be out of dateupdated Feb 2026 | Apr 2022 | granted Jan 2023 | Feb 2026 | Lewes | 9.2 |
| Colbrans Farm Estate, Laughtonsolar farm | solar farm | 40 | approved, not builtupdated Feb 2026 | Dec 2024 | granted Jul 2025 | Feb 2026 | Wealden | 9.9 |
| Colbrans Farm Estate, Laughtonbattery storage | battery storage | 30 | approved, not builtupdated Feb 2026 | Dec 2024 | granted Jul 2025 | Feb 2026 | Wealden | 9.9 |
Smaller schemes under 1 MW, mostly rooftop solar (14)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Utopia Leisure Centre, Downsview Crescentrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Nov 2025 | Jun 2025 | granted Aug 2025 | Nov 2025 | Wealden | 0.9 |
| Uckfield Leisure Centrerooftop solar | rooftop solar | — | under constructionupdated Jan 2026 | — | — | Jan 2026 | Wealden | 0.9 |
| Fastener House, Bolton Closerooftop solar | rooftop solar | 0.6 | approved, not builtupdated Sep 2024 | Jul 2024 | granted Sep 2024 | Sep 2024 | Wealden | 1.9 |
| Fastener House, Bolton Close - Batter Storagebattery storage | battery storage | 0 | application submitted may be out of dateupdated Jul 2024 | Jul 2024 | — | Jul 2024 | Wealden | 1.9 |
| Staverton Nursery, Eastbourne Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated May 2023 | Mar 2023 | granted Apr 2023 | May 2023 | Wealden | 5.7 |
| Staverton Nursery, Eastbourne Roadbattery storage | battery storage | — | application submitted may be out of dateupdated Mar 2023 | Mar 2023 | — | Mar 2023 | Wealden | 5.7 |
| Silveroaks Farm, Hawkhurst Lanesolar farm | solar farm | 0.2 | approved, not builtupdated Apr 2025 | Jan 2025 | granted Mar 2025 | Apr 2025 | Wealden | 7.0 |
| School Field, Barcombe Solar Farmsolar farm | solar farm | — | application submittedupdated Mar 2026 | Feb 2026 | — | Mar 2026 | Lewes | 8.3 |
| Ringmer Solar array/Battery storagebattery storage | battery storage | — | approved, not built may be out of dateupdated Feb 2026 | Apr 2022 | granted Jan 2023 | Feb 2026 | Lewes | 9.2 |
| Chailey Heritage School, Haywards Heath Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2025 | Jul 2024 | granted Jul 2024 | Jan 2025 | Lewes | 9.3 |
| Horder Centre, St Johns Roadrooftop solar | rooftop solar | 0.3 | approved, not builtupdated May 2024 | Mar 2024 | granted May 2024 | May 2024 | Wealden | 9.5 |
| Ervomex Limited, Sybron Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Oct 2023 | Sep 2023 | granted Oct 2023 | Oct 2023 | Wealden | 9.8 |
| Servomex Limited, Sybron Wayrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jan 2025 | Oct 2024 | granted Dec 2024 | Jan 2025 | Wealden | 9.8 |
| Freshfield Lane Brickworks, Freshfield Lanerooftop solar | rooftop solar | 0.3 | approved, not builtupdated Feb 2026 | Sep 2025 | granted Jan 2026 | Feb 2026 | Mid Sussex | 9.9 |
Distance from the average position of the TN22 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 8 | 1 | 4 | 2 | 1 | 62.7 |
| Rooftop solar | 9 | 0 | 9 | 0 | 0 | 2.3 |
| Battery storage | 5 | 2 | 3 | 0 | 0 | 630 |
MW in pipeline: pending, approved and under-construction capacity.
How Wealden decides solar, wind and battery applications
| Applications | Wealden | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 35 | 10,236 |
| Refused | 4 (11%) | 19% |
| Solar refused | 3 of 28 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 0 of 6 | 16% |
| Median time from submission to decision | 11.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 2 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TN22, 5 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.