Tomkins Farm (5 MW solar farm)

Tomkins Farm is a 5 MW solar farm project in Lewes, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: refused on appeal on 18 April 2016; the record was last updated on 4 May 2016.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
refused on appealstatus in REPD
4 May 2016record last updated
Lewescouncil area

Planning timeline

DateStage
21 April 2015Application submitted
30 July 2015Refused by the planning authority
5 November 2015Appeal lodged
18 April 2016Appeal refused

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
refused on appeal
Record last updated
4 May 2016
Operator or applicant
Hadstone Energy
Planning authority
Lewes
Planning application reference
LW/15/0292
Appeal reference
APP/P1425/W/15/3135238
Address (REPD)
Tomkins Farm, Cinder Hill, North Chailey
Council area (by location)
Lewes
Time to decision
14 weeks
REPD reference
5885

Who decides

Lewes has 6 decided solar, wind or battery applications in REPD — too few for a refusal rate (we show one from 10 decisions). Across all UK planning authorities 19% of 10,236 decisions were refusals.

Other large projects within 10 km

ProjectTypeMWStatuskm
Uckfield Solar Electric Forecourtsolar farm5.5approved, not built5.8
Ringmer Solar array/Battery storagesolar farm17approved, not built6.6
Land At Chiddinglye Farmsolar farm5operational6.9
Bentley Estatesolar farm5operational8.0
Stable Green, Sand Hill Lanebattery storage600approved, not built9.5

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9527, 0.0002).