Energy Projects Near You

Uckfield Solar Electric Forecourt (5.5 MW)

Uckfield Solar Electric Forecourt is a 5.5 MW solar farm project in Wealden, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 16 March 2021, not yet built; the record was last updated on 30 April 2021. REPD also records that the planning permission expired on 16 March 2024, so the project may not go ahead in this form. Check the planning authority's register for the latest position.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5.5 MWsolar farm
approved, not builtmay be out of datestatus in REPD
30 April 2021record last updated
Wealdencouncil area

REPD also records that the planning permission expired on 16 March 2024, so the project may not go ahead in this form.

Planning timeline

DateStage
3 August 2020Application submitted
16 March 2021Planning permission granted
16 March 2024Permission expired

Project details

Technology
solar farm
Capacity
5.5 MW
Status (REPD)
approved, not built
Record last updated
30 April 2021
Operator or applicant
Gridserve Sustainable Energy
Planning authority
Wealden
Planning application reference
WD/2020/1244/MAJ
Site area
9.4 ha
Address (REPD)
Land At Copwood Barn, Rocks Road, Uckfield, East Sussex
Council area (by location)
Wealden
Time to decision
32 weeks
REPD reference
7447

Who decides

ApplicationsWealdenUK
Decided applications (solar, wind, battery)3510,236
Refused4 (11%)19%
Solar refused3 of 2812%
Onshore wind refused1 of 145%
Battery storage refused0 of 616%
Median time from submission to decision11.6 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Bentley Estatesolar farm5operational4.5
Stable Green, Sand Hill Lanebattery storage600approved, not built4.9
Tomkins Farmsolar farm5refused on appeal5.8
Ringmer Solar array/Battery storagesolar farm17approved, not built7.4
Colbrans Farm Estate, Laughtonsolar farm40approved, not built8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9689, 0.0793).