Bentley Estate (5 MW solar farm)

Bentley Estate is a 5 MW solar farm project in Wealden, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 17 December 2015; the record was last updated on 27 February 2017.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

5 MWsolar farm
operationalstatus in REPD
27 February 2017record last updated
Wealdencouncil area

Planning timeline

DateStage
20 June 2014Application submitted
28 August 2014Refused by the planning authority
23 March 2015Appeal lodged
23 July 2015Planning permission granted
23 July 2015Appeal allowed
23 September 2015Construction started
17 December 2015Operational

Project details

Technology
solar farm
Capacity
5 MW
Status (REPD)
operational
Record last updated
27 February 2017
Operator or applicant
Lightsource Renewable Energy
Planning authority
Wealden
Planning application reference
WD/2014/1245/MAJ
Site area
9.1 ha
Address (REPD)
BENTLEY ESTATE, UCKFIELD, EAST SUSSEX, TN22 5QP
Council area (by location)
Wealden
Time to decision
57 weeks
REPD reference
2132

Who decides

ApplicationsWealdenUK
Decided applications (solar, wind, battery)3510,236
Refused4 (11%)19%
Solar refused3 of 2812%
Onshore wind refused1 of 145%
Battery storage refused0 of 616%
Median time from submission to decision11.6 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Stable Green, Sand Hill Lanebattery storage600approved, not built1.9
Colbrans Farm Estate, Laughtonsolar farm40approved, not built4.5
Uckfield Solar Electric Forecourtsolar farm5.5approved, not built4.5
Ringmer Solar array/Battery storagesolar farm17approved, not built5.1
Laughton Levelsolar farm7operational7.3
Tomkins Farmsolar farm5refused on appeal8.0
Lower Mays Farm Solar Farmsolar farm5approved, not built8.3
Horamsolar farm8.1operational8.9
Lower Claverham Farm & Mount Pleasant Farm, Berwick Solar Farmsolar farm49.9refused9.2

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9335, 0.1108).