Energy Projects Near You

Horam (8.1 MW solar farm)

Horam is an 8.1 MW solar farm project in Wealden, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 20 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.1 MWsolar farm
operationalstatus in REPD
20 April 2015record last updated
Wealdencouncil area

Planning timeline

DateStage
7 August 2014Application submitted
19 September 2014Planning permission granted
1 January 2015Construction started
31 March 2015Operational

Project details

Technology
solar farm
Capacity
8.1 MW
Status (REPD)
operational
Record last updated
20 April 2015
Operator or applicant
Vogt Solar
Planning authority
Wealden
Planning application reference
WD/2014/1642
Address (REPD)
Land AND WEST OF HORAM MANOR, HORAM
Council area (by location)
Wealden
Time to decision
6 weeks
REPD reference
2169

Who decides

ApplicationsWealdenUK
Decided applications (solar, wind, battery)3510,236
Refused4 (11%)19%
Solar refused3 of 2812%
Onshore wind refused1 of 145%
Battery storage refused0 of 616%
Median time from submission to decision11.6 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Stable Green, Sand Hill Lanebattery storage600approved, not built7.3
Lower Claverham Farm & Mount Pleasant Farm, Berwick Solar Farmsolar farm49.9refused8.8
Bentley Estatesolar farm5operational8.9
Berwick solar farmsolar farm8.2operational9.5
Colbrans Farm Estate, Laughtonsolar farm40approved, not built9.5
Natewood Farmsolar farm8.9operational9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.9313, 0.2377).