Energy Projects Near You

Solar, wind and battery projects near Mayfield (TN20)

6 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TN20 (Wealden): 5 approved but not yet running, 1 operational. The largest live scheme is Horder Centre, St Johns Road (0.3 MW rooftop solar, approved on 9 May 2024, not yet built), 9.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

6projects within 10 km
0awaiting a decision
5approved, not running
1operational

Projects within 10 km of TN20

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Horamsolar farmsolar farm8.1operationalupdated Apr 2015Aug 2014granted Sep 2014Apr 2015Wealden9.5
Smaller schemes under 1 MW, mostly rooftop solar (5)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Co Op, High Streetrooftop solarrooftop solar0.2approved, not builtupdated Jun 2025Apr 2025granted May 2025Jun 2025Wealden5.1
Ervomex Limited, Sybron Wayrooftop solarrooftop solar0.2approved, not builtupdated Oct 2023Sep 2023granted Oct 2023Oct 2023Wealden5.3
Servomex Limited, Sybron Wayrooftop solarrooftop solar0.2approved, not builtupdated Jan 2025Oct 2024granted Dec 2024Jan 2025Wealden5.3
Silveroaks Farm, Hawkhurst Lanesolar farmsolar farm0.2approved, not builtupdated Apr 2025Jan 2025granted Mar 2025Apr 2025Wealden8.4
Horder Centre, St Johns Roadrooftop solarrooftop solar0.3approved, not builtupdated May 2024Mar 2024granted May 2024May 2024Wealden9.2

Distance from the average position of the TN20 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm201100.2
Rooftop solar404001

MW in pipeline: pending, approved and under-construction capacity.

How Wealden decides solar, wind and battery applications

ApplicationsWealdenUK
Decided applications (solar, wind, battery)3510,236
Refused4 (11%)19%
Solar refused3 of 2812%
Onshore wind refused1 of 145%
Battery storage refused0 of 616%
Median time from submission to decision11.6 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

All projects in Wealden

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.