Energy Projects Near You

Solar, wind and battery projects near Wadhurst (TN5)

2 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TN5 (Wealden): 1 is waiting for a planning decision, 1 approved but not yet running. The largest live scheme is Knockout Print Services, Petteridge Lane (2.5 MW rooftop solar, approved on 16 October 2023, not yet built), 9.3 km away. Source: Renewable Energy Planning Database, July 2026 extract.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

2projects within 10 km
1awaiting a decision
1approved, not running
0operational

Projects within 10 km of TN5

Projects of 1 MW and more (1)

ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Knockout Print Services, Petteridge Lanerooftop solarrooftop solar2.5approved, not builtupdated Oct 2023Aug 2023granted Oct 2023Oct 2023Tunbridge Wells9.3
Smaller schemes under 1 MW, mostly rooftop solar (1)
ProjectTypeMWStatus (REPD)SubmittedDecisionRecord updatedCouncilkm
Dale Hill Hotel & Golf Club, Dale Hill - Ground Mounted Solar Panelssolar farmsolar farm0.3application submittedupdated Oct 2025Sep 2025—Oct 2025Rother4.1

Distance from the average position of the TN5 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.

By type

TypeAllPendingApprovedOperationalRefusedMW in pipeline
Solar farm110000.3
Rooftop solar101002.5

MW in pipeline: pending, approved and under-construction capacity.

How Wealden decides solar, wind and battery applications

ApplicationsWealdenUK
Decided applications (solar, wind, battery)3510,236
Refused4 (11%)19%
Solar refused3 of 2812%
Onshore wind refused1 of 145%
Battery storage refused0 of 616%
Median time from submission to decision11.6 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

All projects in Wealden

Is the status up to date?

32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Check the council's planning register for the latest decision.