Solar, wind and battery projects near Heathfield (TN21)
14 solar, wind or battery projects of 150 kW or more are recorded within 10 km of the centre of TN21 (Wealden): 3 are waiting for a planning decision, 8 approved but not yet running, 2 operational. The largest live scheme is Stable Green, Sand Hill Lane (600 MW battery storage, approved on 31 July 2025, not yet built), 9.2 km away. Source: Renewable Energy Planning Database, July 2026 extract.
Projects within 10 km of TN21
Projects of 1 MW and more (3)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Horamsolar farm | solar farm | 8.1 | operationalupdated Apr 2015 | Aug 2014 | granted Sep 2014 | Apr 2015 | Wealden | 3.5 |
| Stone Hillsolar farm | solar farm | 2.6 | operationalupdated Jun 2014 | Oct 2013 | granted Jan 2014 | Jun 2014 | Wealden | 4.9 |
| Stable Green, Sand Hill Lanebattery storage | battery storage | 600 | approved, not builtupdated Nov 2025 | Jan 2025 | granted Jul 2025 | Nov 2025 | Wealden | 9.2 |
Smaller schemes under 1 MW, mostly rooftop solar (11)
| Project | Type | MW | Status (REPD) | Submitted | Decision | Record updated | Council | km |
|---|---|---|---|---|---|---|---|---|
| Co Op, High Streetrooftop solar | rooftop solar | 0.2 | approved, not builtupdated Jun 2025 | Apr 2025 | granted May 2025 | Jun 2025 | Wealden | 1.8 |
| Silveroaks Farm, Hawkhurst Lanesolar farm | solar farm | 0.2 | approved, not builtupdated Apr 2025 | Jan 2025 | granted Mar 2025 | Apr 2025 | Wealden | 5.2 |
| Hellingly Hospital, The Driverooftop solar | rooftop solar | 0.3 | approved, not builtupdated Jan 2026 | Sep 2025 | granted Oct 2025 | Jan 2026 | Wealden | 7.6 |
| Chilsham Farm Nursery, Chilsham Lanesolar farm | solar farm | 0.2 | approved, not builtupdated Apr 2026 | Dec 2025 | granted Feb 2026 | Apr 2026 | Wealden | 7.9 |
| Swallow Enterprise Park, Diamond Driverooftop solar | rooftop solar | 0.3 | approved, not builtupdated Dec 2023 | Oct 2023 | granted Nov 2023 | Dec 2023 | Wealden | 8.8 |
| Knights Farm West - Waste Vehicle Depot & Solar Farmsolar farm | solar farm | 1 | application submittedupdated Jan 2026 | Nov 2025 | — | Jan 2026 | Wealden | 9.1 |
| Boship Lions Farm Hotel, Lower Dickersolar farm | solar farm | — | application submitted may be out of dateupdated May 2024 | Apr 2024 | — | May 2024 | Wealden | 9.1 |
| Oakwood Business Park, Golden Crossrooftop solar | rooftop solar | 0.8 | application withdrawnupdated Sep 2024 | Mar 2024 | — | Sep 2024 | Wealden | 9.1 |
| Lansdowne Secure Childrens Homerooftop solar | rooftop solar | 0.1 | approved, not built may be out of dateupdated Jun 2021 | Jun 2021 | granted Dec 2021 | Jun 2021 | Wealden | 9.3 |
| Staverton Nursery, Eastbourne Roadrooftop solar | rooftop solar | 0.1 | approved, not builtupdated May 2023 | Mar 2023 | granted Apr 2023 | May 2023 | Wealden | 9.8 |
| Staverton Nursery, Eastbourne Roadbattery storage | battery storage | — | application submitted may be out of dateupdated Mar 2023 | Mar 2023 | — | Mar 2023 | Wealden | 9.8 |
Distance from the average position of the TN21 postcodes, not from your home. Projects of 5 MW and more have their own page with dates and planning history.
By type
| Type | All | Pending | Approved | Operational | Refused | MW in pipeline |
|---|---|---|---|---|---|---|
| Solar farm | 6 | 2 | 2 | 2 | 0 | 1.4 |
| Rooftop solar | 6 | 0 | 5 | 0 | 0 | 1.1 |
| Battery storage | 2 | 1 | 1 | 0 | 0 | 600 |
MW in pipeline: pending, approved and under-construction capacity.
How Wealden decides solar, wind and battery applications
| Applications | Wealden | UK |
|---|---|---|
| Decided applications (solar, wind, battery) | 35 | 10,236 |
| Refused | 4 (11%) | 19% |
| Solar refused | 3 of 28 | 12% |
| Onshore wind refused | 1 of 1 | 45% |
| Battery storage refused | 0 of 6 | 16% |
| Median time from submission to decision | 11.6 weeks | 17.0 weeks |
| Appeals lodged / allowed | 2 / 2 | — |
Is the status up to date?
32% of applications still shown as pending in REPD were submitted more than two years ago, and only 37% of pending records were updated in the last 12 months, so some of them may already have been decided. Near TN21, 3 projects have a status that may be out of date (pending for over two years, or approved with a permission expiry date already passed). Check the council's planning register for the latest decision.