Berwick solar farm (8.2 MW)

Berwick solar farm is an 8.2 MW solar farm project in Wealden, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 31 March 2015; the record was last updated on 1 April 2015.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

8.2 MWsolar farm
operationalstatus in REPD
1 April 2015record last updated
Wealdencouncil area

Planning timeline

DateStage
12 August 2013Application submitted
21 October 2013Planning permission granted
20 October 2014Construction started
31 March 2015Operational

Project details

Technology
solar farm
Capacity
8.2 MW
Status (REPD)
operational
Record last updated
1 April 2015
Operator or applicant
Susenco/Low Carbon
Planning authority
Wealden
Planning application reference
WD/2013/1664/MEA
Site area
30.4 ha
Address (REPD)
Berwick, Polegate, West Sussex
Council area (by location)
Wealden
Time to decision
10 weeks
REPD reference
1963

Who decides

ApplicationsWealdenUK
Decided applications (solar, wind, battery)3510,236
Refused4 (11%)19%
Solar refused3 of 2812%
Onshore wind refused1 of 145%
Battery storage refused0 of 616%
Median time from submission to decision11.6 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Lower Claverham Farm & Mount Pleasant Farm, Berwick Solar Farmsolar farm49.9refused0.7
Wilbees Farmsolar farm5operational2.1
Lower Mays Farm Solar Farmsolar farm5approved, not built2.2
Laughton Levelsolar farm7operational4.1
Natewood Farmsolar farm8.9operational4.4
Colbrans Farm Estate, Laughtonsolar farm40approved, not built5.9
Shepham Lanewind farm7.5operational7.4
Horamsolar farm8.1operational9.5
Bentley Estatesolar farm5operational9.7

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.856, 0.1748).