Energy Projects Near You

Shepham Lane (7.5 MW wind farm)

Shepham Lane is a 7.5 MW wind farm project in Wealden, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: operational since 12 January 2017; the record was last updated on 1 May 2018.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

7.5 MWwind farm
operationalstatus in REPD
1 May 2018record last updated
Wealdencouncil area

Planning timeline

DateStage
18 February 2013Application submitted
9 May 2013Refused by the planning authority
18 December 2013Appeal lodged
7 January 2015Planning permission granted
7 January 2015Appeal allowed
16 August 2016Construction started
12 January 2017Operational

Project details

Technology
wind farm
Capacity
7.5 MW
Status (REPD)
operational
Record last updated
1 May 2018
Operator or applicant
Foresight
Planning authority
Wealden
Planning application reference
WD/2013/0346/MEA
Appeal reference
APP/C1435/A/13/2208526
Turbines
3
Address (REPD)
Land off Shepham Lane, North of A27, Polegate
Council area (by location)
Wealden
Time to decision
98 weeks
REPD reference
4326

Earlier applications for this site

ApplicationMWSubmittedOutcome
Shepham Lane WD/2011/2137/MEA12.530 September 2011withdrawn 17 July 2012

Who decides

ApplicationsWealdenUK
Decided applications (solar, wind, battery)3510,236
Refused4 (11%)19%
Solar refused3 of 2812%
Onshore wind refused1 of 145%
Battery storage refused0 of 616%
Median time from submission to decision11.6 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Natewood Farmsolar farm8.9operational3.0
Suncoast Solar Farmsolar farm20approved, not built4.6
Suncoast Battery Storagebattery storage5approved, not built4.6
Wilbees Farmsolar farm5operational5.8
Berwick solar farmsolar farm8.2operational7.4
Lower Claverham Farm & Mount Pleasant Farm, Berwick Solar Farmsolar farm49.9refused7.6
Lower Mays Farm Solar Farmsolar farm5approved, not built9.6

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8295, 0.2709).