Colbrans Farm Estate, Laughton (40 MW solar farm)

Colbrans Farm Estate, Laughton is a 40 MW solar farm project in Wealden, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 21 July 2025, not yet built; the record was last updated on 16 February 2026.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

40 MWsolar farm
approved, not builtstatus in REPD
16 February 2026record last updated
Wealdencouncil area

Planning timeline

DateStage
18 December 2024Application submitted
21 July 2025Planning permission granted
21 July 2028Permission due to expire (unless work starts)

Project details

Technology
solar farm
Capacity
40 MW
Status (REPD)
approved, not built
Record last updated
16 February 2026
Operator or applicant
Innova
Planning authority
Wealden
Planning application reference
WD/2024/2392/MEA
Site area
102.0 ha
Address (REPD)
Colbrans Farm Estate, Laughton, Lewes
Council area (by location)
Wealden
Time to decision
31 weeks
Contracts for Difference
AR7a
Name in REPD
Colbrans Farm Estate, Laughton - Solar Panels
REPD reference
11681

The scheme also includes 30 MW of battery storage, recorded separately in REPD (approved, not built).

Who decides

ApplicationsWealdenUK
Decided applications (solar, wind, battery)3510,236
Refused4 (11%)19%
Solar refused3 of 2812%
Onshore wind refused1 of 145%
Battery storage refused0 of 616%
Median time from submission to decision11.6 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Laughton Levelsolar farm7operational2.8
Lower Mays Farm Solar Farmsolar farm5approved, not built4.1
Bentley Estatesolar farm5operational4.5
Ringmer Solar array/Battery storagesolar farm17approved, not built4.5
Lower Claverham Farm & Mount Pleasant Farm, Berwick Solar Farmsolar farm49.9refused5.5
Stable Green, Sand Hill Lanebattery storage600approved, not built5.6
Berwick solar farmsolar farm8.2operational5.9
Wilbees Farmsolar farm5operational7.9
Uckfield Solar Electric Forecourtsolar farm5.5approved, not built8.8

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8935, 0.1158).