Moor Hall Farm, Moor Hall Drive (400 MW battery storage)

Moor Hall Farm, Moor Hall Drive is a 400 MW battery storage project in Wealden, England. Its status in the Renewable Energy Planning Database (July 2026 extract) is: approved on 23 September 2025, not yet built; the record was last updated on 7 November 2025.

Data: REPD July 2026 extract · calculated 7 November 2026 · Methodology and sources

400 MWbattery storage
approved, not builtstatus in REPD
7 November 2025record last updated
Wealdencouncil area

Planning timeline

DateStage
24 January 2025Application submitted
23 September 2025Planning permission granted
23 September 2028Permission due to expire (unless work starts)

Project details

Technology
battery storage (stand-alone storage)
Capacity
400 MW
Status (REPD)
approved, not built
Record last updated
7 November 2025
Operator or applicant
Balance Power Projects Limited
Planning authority
Wealden
Planning application reference
WD/2024/2957/MAJ
Address (REPD)
Moor Hall Farm, Moor Hall Drive, Ninfield, Battle
Council area (by location)
Wealden
Time to decision
35 weeks
Name in REPD
Moor Hall Farm, Moor Hall Drive - Battery Energy Storage Facility
REPD reference
16245

Who decides

ApplicationsWealdenUK
Decided applications (solar, wind, battery)3510,236
Refused4 (11%)19%
Solar refused3 of 2812%
Onshore wind refused1 of 145%
Battery storage refused0 of 616%
Median time from submission to decision11.6 weeks17.0 weeks
Appeals lodged / allowed2 / 2—

Other large projects within 10 km

ProjectTypeMWStatuskm
Pashley Farm, Ninfield Roadbattery storage130application submitted1.6
Pashley Farmsolar farm11.5operational1.7
Eastlands Farm, Catsfield - Catsfield Battery Energy Storage Facilitybattery storage240approved, not built2.0
Catsfield Christmas Tree Farm, The Streambattery storage99.9application submitted2.0

Status and dates as recorded in the Renewable Energy Planning Database (July 2026 extract); the database is compiled from public sources and can lag behind council decisions. Location: REPD grid reference (50.8861, 0.4148).